How To Fix PJ170 - Please set finish date to a date later than the start date


SAP Error Message - Details

  • Message type: E = Error

  • Message class: PJ - MPX interface messages (Download and Upload)

  • Message number: 170

  • Message text: Please set finish date to a date later than the start date

  • Show details Hide details
  • What causes this issue?

    You have entered a finish date on the calendar that is before the
    start date.

    System Response

    INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX

    How to fix this error?

    Enter a different finish date.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message PJ170 - Please set finish date to a date later than the start date ?

    The SAP error message PJ170, which states "Please set finish date to a date later than the start date," typically occurs in the context of project management within SAP, particularly when dealing with project definitions, WBS (Work Breakdown Structure) elements, or network activities. This error indicates that the finish date you have entered is earlier than or the same as the start date, which is not logically valid for scheduling.

    Cause:

    1. Incorrect Date Entry: The finish date has been entered incorrectly, either manually or through a data import.
    2. System Configuration: There may be system settings or configurations that are not allowing for the correct date range.
    3. Project Planning Logic: The project planning logic requires that the finish date must always be after the start date to maintain a logical sequence in project scheduling.

    Solution:

    1. Check Dates: Review the start and finish dates you have entered. Ensure that the finish date is indeed later than the start date.
    2. Adjust Dates: If the finish date is incorrect, adjust it to a date that is later than the start date.
    3. Validation: After making changes, validate the entries to ensure that the error does not reoccur.
    4. Consult Documentation: If you are unsure about the correct dates, consult project documentation or stakeholders to confirm the intended schedule.
    5. System Settings: If the issue persists, check with your SAP administrator to ensure that there are no system settings or constraints affecting date entries.

    Related Information:

    • SAP Notes: Check SAP Notes for any known issues or patches related to this error message.
    • Project Management Best Practices: Familiarize yourself with project management best practices to ensure that project timelines are realistic and achievable.
    • Training: If you frequently encounter this error, consider additional training on SAP project management modules to better understand date handling and project scheduling.

    By following these steps, you should be able to resolve the PJ170 error and continue with your project planning in SAP.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author