How To Fix /PF1/MSG_RP_E889 - Specify the base time for calculating the planned execution time


SAP Error Message - Details

  • Message type: E = Error

  • Message class: /PF1/MSG_RP_E -

  • Message number: 889

  • Message text: Specify the base time for calculating the planned execution time

  • Show details Hide details


  • Self-Explanatory Message

    Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.

    To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.

    Unfortunately, there isn't any extra information in this error notice.



    What else can you do?

    First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).

    Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.

    You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.


Smart SAP Assistant

  • What is the cause and solution for SAP error message /PF1/MSG_RP_E889 - Specify the base time for calculating the planned execution time ?

    The SAP error message /PF1/MSG_RP_E889 indicates that the system requires a base time to calculate the planned execution time for a specific operation or task. This error typically arises in the context of production planning or scheduling within SAP, where the system needs a reference point to determine how long a task is expected to take.

    Cause:

    The error is usually caused by one of the following reasons:

    1. Missing Base Time: The base time for the operation or task has not been defined in the relevant master data (e.g., routing, work center).
    2. Incorrect Configuration: The configuration settings for the planning or scheduling process may not be set up correctly, leading to the absence of a base time.
    3. Data Inconsistency: There may be inconsistencies in the data related to the production order, routing, or work center that prevent the system from calculating the planned execution time.

    Solution:

    To resolve this error, you can take the following steps:

    1. Check Master Data:

      • Go to the relevant routing or work center in SAP and ensure that the base time is defined correctly.
      • For routings, check the operation details to ensure that the base time is specified.
      • For work centers, verify that the standard values (e.g., setup time, processing time) are maintained.
    2. Maintain Base Time:

      • If the base time is missing, you will need to enter it. This can typically be done in the transaction codes:
        • CA01 (Create Routing)
        • CA02 (Change Routing)
        • CR01 (Create Work Center)
        • CR02 (Change Work Center)
    3. Review Configuration:

      • Check the configuration settings in the SAP system related to production planning and scheduling. Ensure that all necessary parameters are set up correctly.
    4. Data Consistency Check:

      • Run consistency checks on the relevant master data to identify any discrepancies that may be causing the issue.
    5. Consult Documentation:

      • Refer to SAP documentation or help resources for specific details on how to set up base times and related parameters.
    6. Contact Support:

      • If the issue persists after checking the above points, consider reaching out to your SAP support team or consulting with an SAP expert for further assistance.

    Related Information:

    • Transaction Codes: Familiarize yourself with relevant transaction codes for routing and work center maintenance.
    • SAP Notes: Check for any SAP Notes related to this error message for additional guidance or patches.
    • User Manuals: Review user manuals or training materials related to production planning and scheduling in SAP for best practices.

    By following these steps, you should be able to resolve the error and ensure that the planned execution time can be calculated correctly.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant