How To Fix PEP099 - There a tasks with start date in the past in the task plan.


SAP Error Message - Details

  • Message type: E = Error

  • Message class: PEP - Schedule Manager: Messages

  • Message number: 099

  • Message text: There a tasks with start date in the past in the task plan.

  • Show details Hide details


  • Self-Explanatory Message

    Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.

    To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.

    Unfortunately, there isn't any extra information in this error notice.



    What else can you do?

    First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).

    Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.

    You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.


Smart SAP Assistant

  • What is the cause and solution for SAP error message PEP099 - There a tasks with start date in the past in the task plan. ?

    The SAP error message PEP099 indicates that there are tasks in a project or task plan that have a start date set in the past. This can occur in various SAP modules, particularly in Project System (PS) or Project Management (PM) environments, where task scheduling is critical for project planning and execution.

    Cause:

    1. Incorrect Task Scheduling: The tasks may have been scheduled incorrectly, with start dates that do not align with the current date or project timeline.
    2. Data Entry Errors: Manual entry errors during task creation or modification can lead to past dates being set unintentionally.
    3. Project Delays: If a project has been delayed, tasks that were originally planned to start in the future may now have start dates that fall in the past.
    4. System Configuration Issues: In some cases, system settings or configurations may lead to incorrect date assignments.

    Solution:

    1. Review Task Dates: Check the start dates of the tasks in the task plan. Identify which tasks have start dates in the past.
    2. Update Task Dates: Modify the start dates of the affected tasks to reflect a future date that aligns with the current project timeline.
      • Navigate to the task in the project plan.
      • Change the start date to a valid future date.
    3. Check Dependencies: Ensure that any dependencies or relationships between tasks are also updated accordingly to avoid conflicts.
    4. Re-evaluate Project Schedule: If multiple tasks are affected, consider reviewing the overall project schedule to ensure that it is realistic and achievable.
    5. Consult with Project Stakeholders: If the project has been delayed or if there are significant changes, consult with project stakeholders to realign the project plan.

    Related Information:

    • Transaction Codes: You may use transaction codes like CJ20N (Project Builder) or CJ02 (Change Project) to access and modify project tasks.
    • Project Management Best Practices: Regularly review and update project schedules to reflect current realities and avoid scheduling conflicts.
    • SAP Notes and Documentation: Check SAP Notes for any known issues or patches related to project scheduling and task management.
    • Training and Support: If you frequently encounter this error, consider additional training on project management within SAP or consult with your SAP support team for assistance.

    By addressing the root cause of the error and updating the task dates accordingly, you should be able to resolve the PEP099 error and continue with your project planning activities.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author