Do you have any question about this error?
Message type: E = Error
Message class: OK - Logical database PS
Message number: 007
Message text: No selection possible: WBS elements do not belong to subproject &
The WBS elements do not belong to subproject &V1&.
INCLUDE 'NA_ALLG_NOFUNKTION' OBJECT DOKU ID TX
Enter a WBS element on the selection screen which belongs to subproject
&V1& or make a new selection only using the project definition.
Error message extract from SAP system. Copyright SAP SE.
OK007
- No selection possible: WBS elements do not belong to subproject & ?The SAP error message OK007 ("No selection possible: WBS elements do not belong to subproject &") typically occurs in the context of project management within SAP, particularly when working with Work Breakdown Structure (WBS) elements and subprojects. This error indicates that the WBS elements you are trying to select or manipulate do not belong to the specified subproject.
Causes:
- Incorrect WBS Element Assignment: The WBS elements you are trying to access may not be correctly assigned to the specified subproject.
- Hierarchy Issues: The WBS elements may exist in a different hierarchy or structure that does not include the specified subproject.
- Data Entry Errors: There may be a typographical error in the subproject ID or WBS element ID you are using.
- Authorization Issues: You may not have the necessary permissions to access the specified WBS elements or subproject.
- Project Structure Changes: Changes in the project structure or WBS elements may have occurred, leading to discrepancies.
Solutions:
Verify WBS Element Assignment:
- Check the assignment of the WBS elements to ensure they are correctly linked to the intended subproject. You can do this by navigating to the project structure in SAP and reviewing the hierarchy.
Check Project Hierarchy:
- Use transaction codes like CJ20N (Project Builder) to view the project structure and confirm that the WBS elements are indeed part of the specified subproject.
Correct Data Entry:
- Double-check the IDs you are entering for both the WBS elements and the subproject to ensure there are no typographical errors.
Review Authorizations:
- Ensure that you have the necessary authorizations to access the WBS elements and subproject. If not, contact your SAP security administrator.
Consult with Project Management:
- If there have been recent changes to the project structure, consult with your project management team to understand any modifications that may have affected the WBS elements.
Use SAP Help Documentation:
- Refer to SAP's help documentation or support resources for additional guidance on handling WBS elements and subprojects.
Related Information:
By following these steps, you should be able to identify the cause of the error and implement a solution to resolve it.
Get instant SAP help. Start your 7-day free trial now.
OK006
No selection possible: WBS element & does not belong to subproject &
What causes this issue? WBS element &V1& does not belong to subproject &V2&.System Response INCLUDE 'NA_ALLG_NOFUNKTION' O...
OK005
You cannot select using both sales document and project definition
What causes this issue? You cannot use "project definition" and "sales document" at the same time as selection criteria.System Re...
OK008
You cannot select just a network activity
What causes this issue? You have tried to select network activities only. To avoid unnecessarily long program run times, the system does not allow th...
OK009
Runtime logical database PSJ: &
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.