Do you have any question about this error?
Message type: E = Error
Message class: MW - Messages IS-R / Allocation Tables
Message number: 456
Message text: Order quantity exceeds the open target quantity of contract
Allocation table item &V1& was created referencing contract &V2&. The
order quantity of the item is greater than the target quantity
(&V3& &V4&) of the contract.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Change the order quantity in the item if appropriate.
Error message extract from SAP system. Copyright SAP SE.
MW456
- Order quantity exceeds the open target quantity of contract ?The SAP error message MW456 ("Order quantity exceeds the open target quantity of contract") typically occurs when you are trying to create or process a purchase order or a sales order that exceeds the available quantity specified in a contract. This is often related to the use of contracts in procurement or sales processes, where there is a predefined limit on the quantity that can be ordered.
Cause:
- Contract Limitations: The contract associated with the order has a specified target quantity, and the order quantity you are trying to process exceeds this limit.
- Open Target Quantity: The open target quantity is the remaining quantity that can still be ordered against the contract. If your order exceeds this quantity, the error will be triggered.
- Contract Status: The contract may be in a status that does not allow further orders, or it may have been partially fulfilled, reducing the available quantity.
- Incorrect Data Entry: There may be a mistake in the quantity entered in the order or in the contract details.
Solution:
- Check Contract Details: Review the contract associated with the order to verify the target quantity and the open target quantity. You can do this by navigating to the contract in SAP and checking the relevant fields.
- Adjust Order Quantity: If the order quantity exceeds the open target quantity, you will need to reduce the order quantity to match or be less than the available quantity.
- Update Contract: If necessary, you can negotiate with the supplier to increase the target quantity of the contract, if applicable. This may involve creating a new contract or amending the existing one.
- Check for Previous Orders: Ensure that there are no previous orders that have already consumed the available quantity. You can check the history of orders against the contract.
- Consult with Procurement/Sales Team: If you are unsure about the contract limits or need to make changes, consult with your procurement or sales team for guidance.
Related Information:
By following these steps, you should be able to resolve the MW456 error and proceed with your order processing.
Get instant SAP help. Start your 7-day free trial now.
MW455
&1 &2: Del. date &4 does not comply with validity period of contract &3
What causes this issue? Allocation table item &V2& was created referencing contract &V3&. The order date determined to meet delivery ...
MW454
The supplier for plant &1 is not the same as in the contract
What causes this issue? Allocation table item was created referencing contract &V3&. Vendor &V2& for plant &V1& is not the sa...
MW457
Distribution center &1 does not match plant &4 in the contract item
What causes this issue? Allocation table item &V2& was created referencing contract &V3&. Contract item &V1& is valid for pla...
MW458
Supplier &1 and distribution center &2 are identical
What causes this issue? The supplying and receiving plants are the same. The system issues an error message and will not allow you to continue with t...