Message type: E = Error
Message class: MPN02 - MPN Message: Materials Planning
Message number: 016
Message text: &1 cannot be planned in plant &2 (MRP type &3)
Availability indicator &V3& has been entered for material &V1& for
plant &V2&. This availability indicator has MRP procedure 'N' - not
planned for material requirements. Material requirements planning must
however be possible for
<DS:GLOS.3608C3DABA271348E10000009B38F91F>MPN-MRP sets</>.
Input a different availability indicator or remove the material from
the MPN-MRP set.
Error message extract from SAP system. Copyright SAP SE.
MPN02016
- &1 cannot be planned in plant &2 (MRP type &3) ?The SAP error message MPN02016 indicates that a material cannot be planned in a specific plant due to its MRP (Material Requirements Planning) type. This error typically arises in the context of MRP runs or when trying to create or modify planning data for a material.
Cause:
The error message MPN02016 is triggered when:
- The material is not set up for planning in the specified plant.
- The MRP type assigned to the material does not allow for planning in that plant.
- The material may be marked as "not relevant for planning" or has been set to a status that prevents it from being included in MRP calculations.
- The plant itself may not be set up correctly for MRP processes.
Solution:
To resolve the error, you can take the following steps:
Check Material Master Data:
- Go to the material master record (transaction code MM03) and check the MRP views for the material in the specified plant.
- Ensure that the MRP type is appropriate for the planning strategy you want to use.
Review MRP Type:
- Verify the MRP type assigned to the material. Common MRP types include PD (MRP), VB (Manual Reorder Point), and others. Ensure that the MRP type allows for planning.
- If necessary, change the MRP type to one that supports planning.
Check Plant Settings:
- Ensure that the plant is correctly configured for MRP. This includes checking the plant settings in the configuration (transaction code SPRO) to ensure MRP is activated.
Check Planning Parameters:
- Review the planning parameters for the material, such as lot size, safety stock, and reorder point, to ensure they are set correctly.
Check for Special Stock Indicators:
- If the material is marked as special stock (e.g., consignment, project stock), ensure that the planning settings are appropriate for that stock type.
Consult Documentation:
- Refer to SAP documentation or help resources for specific details on the MRP type and its implications for planning.
Test MRP Run:
- After making the necessary changes, perform a test MRP run to see if the error persists.
Related Information:
By following these steps, you should be able to identify the root cause of the error and implement the necessary changes to resolve it.
Get instant SAP help. Start your 7-day free trial now.
MPN02015
Different &1 in &2 and &3 in plant &4
What causes this issue? The materials &V2& und &V3& both contain different values in field &V1& in plant &V4&.System ...
MPN02014
&1 has special procurement type &3 in plant &2
What causes this issue? The special procurement key &V3& means subcontracting. MPN materials from an <DS:GLOS.3608C3DABA271348E10000009B38...
MPN02017
Plant &3, storage location &4: different MRP indicator in &1, &2
What causes this issue? The material requirements indicators for materials &V1& and &V2& are different for plant &V3&, storag...
MPN02018
&1 does not have an MRP type in plant &2
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...