Do you have any question about this error?
Message type: E = Error
Message class: KV - Variance Analysis for Cost Centers and Cost Objects
Message number: 163
Message text: Product cost collector & has no planned costs
The <DS:GLOS.target_costs>target costs</> in the selected
<DS:GLOS.target_cost_version>target cost version</> are calculated on
the basis of <DS:GLOS.planned_costs>planned costs</>. Planned costs are
calculated for the <DS:GLOS.product_cost_collector>product cost
collector</> by means of a <DS:GLOS.preliminary_costing>preliminary
cost estimate</> for the product cost collector.
However, no preliminary cost estimate for the product cost collector
exists.
No target costs are calculated.
Create a preliminary cost estimate for the product cost collector, or
choose a different target cost version - such as a version in which the
target costs are calculated on the basis of the
<DS:GLOS.standard_cost_estimate>standard cost estimate</> for the
<DS:GLOS.material>material</>.
Error message extract from SAP system. Copyright SAP SE.
KV163
- Product cost collector & has no planned costs ?The SAP error message KV163 indicates that a product cost collector does not have any planned costs associated with it. This can occur in various scenarios, particularly in the context of product costing and controlling in SAP. Here’s a breakdown of the cause, potential solutions, and related information:
Cause:
- No Costing Run Executed: The product cost collector may not have undergone a costing run, which is necessary to generate planned costs.
- Incorrect Configuration: The configuration for the product cost collector may be incorrect or incomplete, leading to the absence of planned costs.
- Missing Master Data: Essential master data (like material master, routing, or bill of materials) may be missing or not properly maintained, which can prevent the calculation of planned costs.
- Costing Variant Issues: The costing variant used may not be set up correctly, or it may not be applicable to the product cost collector in question.
- Data Transfer Issues: There may be issues with data transfer from other modules or systems that could affect the availability of planned costs.
Solution:
- Execute Costing Run: Ensure that a costing run has been executed for the product cost collector. This can be done through transaction codes like CK11N (Create Cost Estimate) or CK40N (Costing Run).
- Check Configuration: Review the configuration settings for the product cost collector in the controlling area. Ensure that all necessary settings are correctly defined.
- Verify Master Data: Check the relevant master data for the product cost collector, including material master records, routing, and bill of materials. Ensure that all required data is complete and accurate.
- Review Costing Variant: Ensure that the costing variant being used is appropriate for the product cost collector and that it is configured correctly.
- Data Consistency Check: Perform a consistency check to ensure that all necessary data is available and correctly linked. This can help identify any missing or incorrect data.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidance on the error message and related processes.
Related Information:
By following these steps, you should be able to identify the cause of the KV163 error and implement the necessary solutions to resolve it.
Get instant SAP help. Start your 7-day free trial now.
KV162
Cannot calculate target costs - itemization missing
What causes this issue? The <DS:GLOS.Sollkosten>target costs</> are determined on the basis of the costs calculated in a <DS:GLOS.Mate...
KV161
WIP or scrap calculation for parallel operation sequences not possible
What causes this issue? If the routing specifies a sequence of operations that are defined as a parallel sequence, this will have the following effec...
KV164
No reporting points found
What causes this issue? You are attempting to do the following: Valuate the scrap confirmed at the reporting points in variance calculation Calculate...
KV165
No target costs in target cost version & - missing plan for & &
What causes this issue? In <DS:GLOS.target_cost_version>target cost version</> &v1&, no <DS:GLOS.target_costs>target costs&...
Click on this link to search all SAP messages.