Do you have any question about this error?
Message type: E = Error
Message class: KEO - Enterprise Organization
Message number: 073
Message text: Cost center &1 is assigned to the wrong controlling area
When carrying out the consistency check for the enterprise
organization, the system found that cost center &V1& in the enterprise
organization is assigned to controlling area &V2&. In the master record
however, cost center &V1& is assigned to controlling area &V3&.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Contact your system administrator.
Error message extract from SAP system. Copyright SAP SE.
KEO073
- Cost center &1 is assigned to the wrong controlling area ?The SAP error message KEO073 indicates that a cost center is assigned to a controlling area that does not match the configuration in the system. This typically occurs when there is a mismatch between the controlling area assigned to the cost center and the controlling area that is being used in a particular transaction or report.
Cause:
- Incorrect Assignment: The cost center is assigned to a different controlling area than the one being used in the transaction.
- Configuration Issues: There may be issues in the configuration of the controlling area or cost center master data.
- Data Migration Issues: If data has been migrated from another system, there may be inconsistencies in the assignments.
- User Error: Users may be trying to post to a cost center that is not valid for the controlling area they are working in.
Solution:
Check Cost Center Assignment:
- Go to the cost center master data (Transaction code: KS03) and verify the controlling area assigned to the cost center.
- Ensure that the cost center is assigned to the correct controlling area that you are trying to use.
Review Controlling Area Settings:
- Check the configuration of the controlling area (Transaction code: OX19) to ensure it is set up correctly.
- Make sure that the controlling area is active and properly configured.
Correct the Transaction:
- If you are trying to post to a cost center in a different controlling area, either change the controlling area in your transaction or select a cost center that belongs to the correct controlling area.
Data Migration Review:
- If this issue arose after a data migration, review the migration process to ensure that cost centers were assigned correctly to their respective controlling areas.
Consult Documentation:
- Refer to SAP documentation or consult with your SAP support team for specific guidance related to your system configuration.
Related Information:
By following these steps, you should be able to resolve the KEO073 error and ensure that cost centers are correctly assigned to their respective controlling areas.
Get instant SAP help. Start your 7-day free trial now.
KEO072
Cost center &1 does not exist in controlling area &2
What causes this issue? When carrying out the consistency check for the enterprise organization, the system found that although cost center &1 in...
KEO071
Profit center &1 is not assigned to company code &2
What causes this issue? When carrying out the consistency check for the enterprise organization, the system found that profit center &V1& in ...
KEO074
Cost center &1 is not assigned to company code &2
What causes this issue? When carrying out the consistency check for the enterprise organization, the system found that in the enterprise organization...
KEO075
Cost center &1 does not belong to profit center &2
What causes this issue? When carrying out the consistency check for the enterprise organization, the system found that in the enterprise organization...
Click on this link to search all SAP messages.