  • What causes this issue?

    In Profitability Analysis (CO-PA), the system tried to valuate a line
    item using the <ZH>future standard cost estimate</>.
    In order to determine the <ZH>future plan period</>, the system needs
    to read the valuation segment of the material master.
    The system has found that the future plan period is not filled for
    product <ZH>"&V1&"</> in plant <ZH>"&V2&"</>.

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.

    <DS:TRAN.MM03>Display material (View: Costing)</>
    The system looked for the material cost estimate using costing key
    <ZH>"&V3&"</>, as defined in the
    <DS:SIMG.SIMG_CFMENUORKEKE40>Customizing settings</> for CO-PA.

    System Response

    The document cannot be processed.

    How to fix this error?

    Contact your system administrator.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message KE349 - Valuation with material cost estimate: error with product "&1" ?

    The SAP error message KE349 indicates that there is an issue with the valuation of a product during the material cost estimate process. This error typically arises in the context of controlling (CO) and product costing modules when the system encounters a problem with the product specified in the error message.

    Cause:

    The error can be caused by several factors, including:

    1. Missing Master Data: The material master data for the product may be incomplete or missing. This includes missing cost estimates, valuation classes, or other relevant data.

    2. Incorrect Configuration: There may be configuration issues in the controlling area, such as incorrect settings for cost centers, internal orders, or product costing variants.

    3. Costing Variant Issues: The costing variant used for the material cost estimate may not be properly defined or may not have the necessary settings.

    4. Material Status: The material may have a status that prevents it from being included in the cost estimate, such as being marked as inactive or blocked.

    5. Data Consistency Issues: There may be inconsistencies in the data related to the product, such as discrepancies between the material master and the cost estimate.

    Solution:

    To resolve the KE349 error, you can take the following steps:

    1. Check Material Master Data:

      • Go to the material master (transaction code MM03) and verify that all necessary data is complete and correct.
      • Ensure that the valuation class and costing data are properly maintained.
    2. Review Costing Variant:

      • Check the costing variant settings (transaction code OKKN) to ensure that it is correctly configured for the product and that all necessary parameters are set.
    3. Validate Configuration:

      • Review the configuration settings in the controlling area (transaction code OKKP) to ensure that they are correct and consistent with the product costing requirements.
    4. Check Material Status:

      • Verify the status of the material to ensure it is active and not blocked for costing.
    5. Run Consistency Checks:

      • Use transaction CKR1 to run consistency checks on the cost estimates and material master data to identify any discrepancies.
    6. Recreate Cost Estimate:

      • If necessary, try to recreate the cost estimate for the product to see if the error persists.

    Related Information:

    • Transaction Codes:

      • MM03: Display Material Master
      • CK11N: Create Material Cost Estimate
      • CK40N: Change Material Cost Estimate
      • OKKN: Costing Variants
      • OKKP: Controlling Area Settings
      • CKR1: Consistency Check for Cost Estimates
    • SAP Notes: Check SAP Notes related to KE349 for any specific patches or updates that may address known issues.

    • Documentation: Refer to SAP Help documentation for detailed information on product costing and material valuation processes.

    By following these steps, you should be able to identify and resolve the underlying issue causing the KE349 error in SAP.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant