Message type: E = Error
Message class: K8 - CO Planning: Messages for Function Group KAPP
Message number: 138
Message text: The price for resource &1 has been defined using different currencies
The price for resource &V1& has been defined using different
currencies. However, in CO Planning, you are only allowed to use one
currency per fiscal year.
In planning, the R/3 System takes a resource price of zero for the
valuation.
Maintain valid prices for resource &V1& for WBS element &V2&, fiscal
year &V3&, version &V4&, so that the price determination strategy finds
the price in only one currency.
You can analyze the price determination if you activate condition
analysis for the valuation variants used for version &V4& in fiscal
year &V3&.
Error message extract from SAP system. Copyright SAP SE.
K8138
- The price for resource &1 has been defined using different currencies ?The SAP error message K8138 indicates that there is a discrepancy in the currency settings for a resource in the system. Specifically, it means that the price for a resource has been defined in different currencies, which can lead to inconsistencies and issues in cost calculations and reporting.
Cause: Multiple Currency Definitions: The resource in question has been assigned prices in different currencies, which is not allowed in the context of the specific transaction or configuration you are working with.
Configuration Issues: There may be a configuration issue in the controlling area or the master data settings for the resource. Data Entry Errors: Manual entry errors during the creation or maintenance of the resource master data could lead to this issue.
Solution: Check Resource Master Data: Go to the resource master data (transaction code CR01 or CR02) and check the pricing information for the resource identified by &1 in the error message. Ensure that all price entries for
Get instant SAP help. Sign up for our Free Essentials Plan.
K8137
The price for resource &1 has been defined using different currencies
What causes this issue? The price for resource &V1& has been defined using different currencies. However, in CO Planning, you are only allowe...
K8136
The price for resource &1 has been defined using different currencies
What causes this issue? The price for resource &V1& has been defined using different currencies. However, in CO Planning, you are only allowe...
K8139
Unit & of the recipe price or recipe unit is not possible
What causes this issue? You have entered the value &V1& for the unit of the recipe price in CO area- or object currency, or you have entered ...
K8140
The price for resource &1 is not defined in periods &2 &3
What causes this issue? The system cannot determine the resource price.System Response Processing is terminated.How to fix this error? Check whethe...
Click on this link to search all SAP messages.