Do you have any question about this error?
Message type: E = Error
Message class: IP - Messages for preventive maintenance
Message number: 738
Message text: Enter an end date for scheduling that is after the current date
You are trying to enter <LS>End Date for Scheduling</> &V1& that is
before the current date.
The system will cancel processing.
You need to define an <LS>End Date for Scheduling</> that is after the
current date.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
IP738
- Enter an end date for scheduling that is after the current date ?The SAP error message IP738, which states "Enter an end date for scheduling that is after the current date," typically occurs in the context of scheduling maintenance plans or work orders in SAP PM (Plant Maintenance) or similar modules. This error indicates that the end date you have entered for a scheduling operation is not valid because it is set to a date that is either in the past or the same as the current date.
Cause:
- Invalid Date Entry: The end date you have entered is either earlier than or equal to the current date.
- System Date: The system date may not be set correctly, leading to confusion about what constitutes a valid date.
- Configuration Issues: There may be configuration settings in the scheduling parameters that enforce strict date validation.
Solution:
Check the End Date: Ensure that the end date you are entering is indeed after the current date. You can do this by:
- Comparing the date you entered with the current date displayed in the system.
- Using a date picker or calendar tool within SAP to select a valid future date.
Adjust the Date: If the end date is incorrect, modify it to a future date that meets the scheduling requirements.
Verify System Date: Check the system date to ensure it is set correctly. If the system date is incorrect, you may need to contact your system administrator to correct it.
Review Scheduling Parameters: If you have access, review the configuration settings related to scheduling in SAP to ensure there are no restrictions that could be causing this error.
Consult Documentation: If you are unsure about the scheduling process or the required date formats, refer to SAP documentation or user manuals for guidance.
Related Information:
By following these steps, you should be able to resolve the IP738 error and successfully enter a valid end date for your scheduling needs in SAP.
Get instant SAP help. Start your 7-day free trial now.
IP737
Enter a start of cycle date that is before the end date for scheduling
What causes this issue? You are trying to enter <LS>Start of Cycle</> date &V1& that is after <LS>End Date for Scheduling&l...
IP736
Enter an end date for scheduling that is after the start of cycle date
What causes this issue? You are trying to enter <LS>End Date for Scheduling</> &V1& that is before <LS>Start of Cycle</&...
IP739
Define the end date for scheduling for the maintenance plan
What causes this issue? The maintenance plan from which you would like to copy has an <LS>End Date for Scheduling</> value which is in th...
IP740
End counter for scheduling is lower than the last counter reading
What causes this issue? You are trying to enter <LS>End Counter for Scheduling</> &V1& &V3& which is lower than last coun...