Do you have any question about this error?
Message type: E = Error
Message class: IP - Messages for preventive maintenance
Message number: 429
Message text: Call horizon > 100% is not allowed
You have entered an opening period of greater than 100%.
The maximum possible value is 100%.
The call is made on the planned date in the case of an opening period
of 100%; when the opening period is 0%, the call is made when the
previous call is confirmed as completed.
Correct your entry.
Error message extract from SAP system. Copyright SAP SE.
IP429
- Call horizon > 100% is not allowed ?The SAP error message IP429 "Call horizon > 100% is not allowed" typically occurs in the context of production planning and scheduling, particularly when dealing with capacity planning in SAP's Integrated Planning (IP) module. This error indicates that the planned capacity utilization exceeds 100%, which is not permissible in the system.
Cause:
- Excessive Demand: The planned production or demand exceeds the available capacity of the resources (work centers, machines, etc.).
- Incorrect Planning Parameters: The planning parameters or settings may not be correctly configured, leading to unrealistic capacity utilization.
- Overlapping Orders: Multiple production orders may be scheduled to run simultaneously on the same resource, causing the total utilization to exceed 100%.
- Capacity Constraints: The capacity of the work center may not be sufficient to handle the planned workload.
Solution:
Review Capacity Planning:
- Check the capacity of the relevant work centers and ensure that they are correctly defined in the system.
- Adjust the available capacity if necessary, considering factors like shifts, maintenance, and downtime.
Adjust Production Plans:
- Re-evaluate the production plan to ensure that the demand does not exceed the available capacity.
- Consider rescheduling or delaying some production orders to balance the load.
Modify Planning Parameters:
- Review and adjust the planning parameters in the system to ensure they reflect realistic production capabilities and constraints.
Use Capacity Evaluation Tools:
- Utilize SAP's capacity evaluation tools to analyze the load on work centers and identify bottlenecks.
- Use transaction codes like CM01 (Capacity Planning) to visualize and manage capacity utilization.
Check for Overlapping Orders:
- Ensure that there are no overlapping production orders that could be causing the capacity to exceed 100%.
- If necessary, stagger the start times of production orders to avoid conflicts.
Consult Documentation:
- Refer to SAP documentation or help resources for specific guidance on capacity planning and the IP module.
Related Information:
By addressing the underlying causes and implementing the suggested solutions, you should be able to resolve the IP429 error and ensure that your production planning aligns with available capacity.
Get instant SAP help. Start your 7-day free trial now.
IP428
Scheduling record already confirmed
What causes this issue? You are trying to confirm a <GL:maintenance_call>maintenance call</> that has already been confirmed.System Respo...
IP427
New completion confirmation date < start date &
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
IP430
The first call date has been reached
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
IP431
The last call date has been reached
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.