How To Fix ICH_KANBAN040 - No control cycle control key found for external procurement (table TPK02)


SAP Error Message - Details

  • Message type: E = Error

  • Message class: ICH_KANBAN - Messages for Kanban Master Data Transmission

  • Message number: 040

  • Message text: No control cycle control key found for external procurement (table TPK02)

  • Show details Hide details


  • Self-Explanatory Message

    Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.

    To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.

    Unfortunately, there isn't any extra information in this error notice.



    What else can you do?

    First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).

    Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.

    You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.


Smart SAP Assistant

  • What is the cause and solution for SAP error message ICH_KANBAN040 - No control cycle control key found for external procurement (table TPK02) ?

    The SAP error message ICH_KANBAN040 indicates that there is no control cycle control key found for external procurement in the table TPK02. This error typically arises in the context of Kanban processing, particularly when dealing with external procurement scenarios.

    Cause:

    1. Missing Control Cycle: The primary cause of this error is that there is no control cycle defined for the material in question in the TPK02 table. The control cycle is essential for managing the Kanban process, and if it is not set up correctly, the system cannot process the Kanban signals.
    2. Incorrect Configuration: There may be an issue with the configuration of the Kanban control cycle for external procurement. This could be due to missing entries or incorrect settings in the configuration.
    3. Material Master Data: The material master data may not be correctly set up for Kanban processing, leading to the absence of a control key.

    Solution:

    1. Check Control Cycle Configuration:

      • Go to the transaction code PK01 (Create Control Cycle) or PK02 (Change Control Cycle) in SAP.
      • Verify if a control cycle exists for the material and the relevant plant. If it does not exist, you will need to create a new control cycle.
      • Ensure that the control cycle is correctly configured for external procurement.
    2. Review Material Master Data:

      • Use transaction code MM03 to display the material master data.
      • Check the relevant views (e.g., MRP, Purchasing) to ensure that the material is set up for Kanban processing.
      • Ensure that the procurement type is set correctly (e.g., external procurement).
    3. Check Table TPK02:

      • You can use transaction code SE16N to view the contents of the TPK02 table.
      • Look for entries related to the material and plant in question. If there are no entries, you will need to create a control cycle.
    4. Consult Documentation: If you are unsure about the configuration steps, refer to SAP documentation or consult with your SAP functional consultant for guidance on setting up Kanban control cycles.

    Related Information:

    • Kanban Control Cycle: A Kanban control cycle is a key component in the Kanban process, defining how materials are managed and replenished.
    • External Procurement: This refers to the process of acquiring materials from external suppliers rather than producing them in-house.
    • SAP Modules: This error is typically encountered in the SAP PP (Production Planning) and MM (Materials Management) modules.

    By following these steps, you should be able to resolve the ICH_KANBAN040 error and ensure that your Kanban process for external procurement is functioning correctly.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author