Do you have any question about this error?
Message type: E = Error
Message class: GP - FI-SL and CO planning
Message number: 150
Message text: Combination with & & has already been planned
You have entered a new combination with value &V2& for dimension &V1&.
However, this combination has already been created before calling up
this planning function.
The amounts from the data base are defaulted in the value and quantity
fields. The system ignores the previous entries for values and
quantities.
Enter the values and quantities again if you do not want the amounts
from the data base.
Error message extract from SAP system. Copyright SAP SE.
GP150
- Combination with & & has already been planned ?The SAP error message GP150 ("Combination with & & has already been planned") typically occurs in the context of SAP's Project System (PS) or related modules when there is an attempt to plan or allocate resources, costs, or other elements that have already been planned for a specific combination of parameters (like project, WBS element, or activity).
Cause:
- Duplicate Planning: The error indicates that the system has detected an attempt to plan a combination of elements (e.g., a specific WBS element or activity) that has already been planned in the system.
- Data Integrity: This is a safeguard to maintain data integrity and prevent double planning, which could lead to inconsistencies in project data.
- Locked Entries: Sometimes, the entries may be locked due to ongoing processes or transactions, leading to this error when trying to re-plan.
Solution:
- Check Existing Plans: Review the existing planning entries for the specific combination of elements. You can do this by navigating to the relevant planning transaction (like CJ20N for project planning) and checking the planned values.
- Adjust Planning: If you need to change the planning, you may need to adjust or delete the existing planning entries before attempting to re-plan.
- Use Different Combinations: If applicable, consider using a different combination of parameters that has not been planned yet.
- Consult with Team: If you are unsure about the existing plans, consult with your project team or the person responsible for project planning to understand the current status.
- Transaction Lock: If the error is due to a lock, wait for the transaction to complete or check with your SAP administrator to see if the lock can be released.
Related Information:
If the issue persists after trying the above solutions, it may be beneficial to reach out to your SAP support team for further assistance.
Get instant SAP help. Start your 7-day free trial now.
GP149
No planning data has been entered or the master data is invalid
What causes this issue? You have selected planning objects or currency units for which no planning data has yet been entered, or no valid master data...
GP148
An amount has not yet been distributed
What causes this issue? Either you have not entered a value or the positive and negative values cancel each other out. You can only use a current di...
GP151
Create document type &
What causes this issue? The document type assigned to your planning parameter does not exist.System Response Create document type &V1& in ta...
GP152
Document type & is not supported for planning
What causes this issue? Separate document types are used for planning and actual data. The document type assigned to your planning parameter is not ...
Click on this link to search all SAP messages.