How To Fix GP150 - Combination with & & has already been planned


SAP Error Message - Details

  • Message type: E = Error

  • Message class: GP - FI-SL and CO planning

  • Message number: 150

  • Message text: Combination with & & has already been planned

  • Show details Hide details
  • What causes this issue?

    You have entered a new combination with value &V2& for dimension &V1&.
    However, this combination has already been created before calling up
    this planning function.

    System Response

    The amounts from the data base are defaulted in the value and quantity
    fields. The system ignores the previous entries for values and
    quantities.

    How to fix this error?

    Enter the values and quantities again if you do not want the amounts
    from the data base.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message GP150 - Combination with & & has already been planned ?

    The SAP error message GP150 ("Combination with & & has already been planned") typically occurs in the context of SAP's Project System (PS) or related modules when there is an attempt to plan or allocate resources, costs, or other elements that have already been planned for a specific combination of parameters (like project, WBS element, or activity).

    Cause:

    1. Duplicate Planning: The error indicates that the system has detected an attempt to plan a combination of elements (e.g., a specific WBS element or activity) that has already been planned in the system.
    2. Data Integrity: This is a safeguard to maintain data integrity and prevent double planning, which could lead to inconsistencies in project data.
    3. Locked Entries: Sometimes, the entries may be locked due to ongoing processes or transactions, leading to this error when trying to re-plan.

    Solution:

    1. Check Existing Plans: Review the existing planning entries for the specific combination of elements. You can do this by navigating to the relevant planning transaction (like CJ20N for project planning) and checking the planned values.
    2. Adjust Planning: If you need to change the planning, you may need to adjust or delete the existing planning entries before attempting to re-plan.
    3. Use Different Combinations: If applicable, consider using a different combination of parameters that has not been planned yet.
    4. Consult with Team: If you are unsure about the existing plans, consult with your project team or the person responsible for project planning to understand the current status.
    5. Transaction Lock: If the error is due to a lock, wait for the transaction to complete or check with your SAP administrator to see if the lock can be released.

    Related Information:

    • Transaction Codes: Familiarize yourself with relevant transaction codes such as CJ20N (Project Builder), CJ02 (Change Project), or CJ03 (Display Project) to manage project planning.
    • SAP Notes: Check SAP Notes for any specific patches or updates related to this error message, as there may be known issues or fixes provided by SAP.
    • Documentation: Review SAP documentation or help files related to project planning and resource management for further insights into handling planning errors.

    If the issue persists after trying the above solutions, it may be beneficial to reach out to your SAP support team for further assistance.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating