Message type: E = Error
Message class: FINS_FI_MPROJ - Mass Data Project
Message number: 078
Message text: Package/Org.Unit &1 not processed due to current status of activity &2
The package / organizational unit &V1& was excluded from processing
because the corresponding status of activity &V2& doesn't allow for any
changes.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Depending on the current action, you need to either run or <LS>Reset</>
activity &V2& for the package / organizational unit &V1& in the project
cockpit first.
Error message extract from SAP system. Copyright SAP SE.
FINS_FI_MPROJ078
- Package/Org.Unit &1 not processed due to current status of activity &2 ?The SAP error message FINS_FI_MPROJ078 indicates that a specific package or organizational unit (Org. Unit) cannot be processed due to the current status of an activity. This error typically arises in the context of project management or financial transactions within SAP, particularly when dealing with project-related activities.
Cause:
The error can occur due to several reasons, including:
Activity Status: The activity associated with the package or Org. Unit may be in a status that does not allow further processing. For example, it could be completed, closed, or in a state that restricts changes or updates.
Authorization Issues: The user may not have the necessary authorizations to process the activity or package.
Configuration Issues: There may be configuration settings in the project management or financial modules that prevent the processing of the specified package or Org. Unit.
Data Integrity Issues: There could be inconsistencies or missing data related to the project or activity that need to be resolved.
Solution:
To resolve the error, consider the following steps:
Check Activity Status: Review the status of the activity associated with the package or Org. Unit. If it is in a completed or closed state, you may need to reopen it or create a new activity if applicable.
Review Authorizations: Ensure that the user attempting to process the package has the necessary authorizations. You may need to consult with your SAP security team to verify and adjust user roles if needed.
Consult Configuration Settings: Check the configuration settings related to project management and financial transactions. Ensure that the settings allow for the processing of the specified package or Org. Unit.
Data Validation: Validate the data associated with the project or activity. Look for any missing or inconsistent data that may be causing the issue. Correct any discrepancies found.
SAP Notes and Documentation: Search for relevant SAP Notes or documentation that may provide additional insights or specific fixes related to this error message.
Contact SAP Support: If the issue persists after performing the above checks, consider reaching out to SAP Support for further assistance. Provide them with the error message details and any relevant context to expedite the troubleshooting process.
Related Information:
By following these steps, you should be able to identify the root cause of the error and implement an appropriate solution.
Get instant SAP help. Sign up for our Free Essentials Plan.
FINS_FI_MPROJ077
Package/Org.Unit &1 not processed due to current user selection
What causes this issue? The operation was run with defined selection criteria that restricted, for example, certain packages or organizational units....
FINS_FI_MPROJ076
Event '&1' is only for automatic activities. &2 is a manual activity
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
FINS_FI_MPROJ079
Package/Org.Unit &1 was already processed; it can't be processed again
What causes this issue? Since the current operation was already completed for package / organizational unit &V1& for activity &V2&, i...
FINS_FI_MPROJ080
No package/org.unit can be processed because activity &1 hasn't processed
What causes this issue? The current operation has not yet been completed for activity &V1&. The project cockpit consists of both manual and n...
Click on this link to search all SAP messages.