How To Fix FINS_CFIN_BC_V025 - Activation status of plants abroad does not match in source and target


SAP Error Message - Details

  • Message type: E = Error

  • Message class: FINS_CFIN_BC_V - Business Configuration Validations

  • Message number: 025

  • Message text: Activation status of plants abroad does not match in source and target

  • Show details Hide details
  • What causes this issue?

    If plants abroad are activated in the source system they must also be
    activated in the target system.

    System Response

    The posting cannot be completed in the target system.

    How to fix this error?

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.

    Procedure for System Administrators

    Check the status for plants abroad &V1& in the target system in the
    activity
    <DS:SIMG.SIMG_CFORFBWERK>Activate Plants Abroad</>and compare it with
    the status in the source system.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message FINS_CFIN_BC_V025 - Activation status of plants abroad does not match in source and target ?

    The SAP error message FINS_CFIN_BC_V025 indicates that there is a mismatch in the activation status of plants between the source and target systems during the Central Finance (CFIN) process. This typically occurs when you are trying to replicate or activate data for plants that are set up differently in the source and target systems.

    Cause:

    1. Inconsistent Plant Activation: The plant in the source system may be activated or deactivated, while the corresponding plant in the target system has a different activation status.
    2. Configuration Issues: There may be discrepancies in the configuration settings for the plants in the source and target systems.
    3. Data Replication Issues: If there have been changes in the source system that have not been reflected in the target system, this can lead to mismatches.
    4. Transport Issues: If the configuration changes were not properly transported from the development to the production environment, it could lead to inconsistencies.

    Solution:

    1. Check Plant Activation Status: Verify the activation status of the plants in both the source and target systems. Ensure that they match.

      • In the target system, you can check the activation status in the relevant configuration settings (e.g., in the Customizing settings for Central Finance).
    2. Synchronize Configuration: If there are discrepancies, update the configuration in either the source or target system to ensure they match.

      • If a plant is activated in the source but not in the target, you may need to activate it in the target system.
      • Conversely, if a plant is deactivated in the source but activated in the target, you may need to deactivate it in the target system.
    3. Data Replication: Ensure that all relevant data has been replicated correctly from the source to the target system. You may need to re-trigger the replication process if necessary.

    4. Transport Changes: If the issue is due to transport problems, ensure that all necessary changes have been transported correctly to the target system.

    5. Consult Documentation: Refer to SAP documentation or notes related to Central Finance for any specific instructions or known issues regarding plant activation.

    6. SAP Support: If the issue persists after checking the above points, consider reaching out to SAP support for further assistance.

    Related Information:

    • Central Finance (CFIN): A solution that allows organizations to consolidate financial data from multiple systems into a central system.
    • Plant Activation: The process of enabling a plant in the SAP system to allow for transactions and data processing.
    • SAP Notes: Check for any relevant SAP Notes that may address this specific error or provide additional troubleshooting steps.

    By following these steps, you should be able to resolve the FINS_CFIN_BC_V025 error and ensure that the activation statuses of the plants are consistent between the source and target systems.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author