Message type: E = Error
Message class: FARR_CONTR_LIFECYCLE - Message from Contract Lifecyle (RAR 2.0 Object Model)
Message number: 095
Message text: POB &1: Freeze date &2 must be after the POB start date &3.
POB &v1&: Freeze date &v2& must be after the POB start date &v3&. Adjust
the freeze period &v4&.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
FARR_CONTR_LIFECYCLE095
- POB &1: Freeze date &2 must be after the POB start date &3. ?The SAP error message FARR_CONTR_LIFECYCLE095 indicates that there is a conflict with the freeze date and the start date of a Project Object (POB). Specifically, the error states that the freeze date must be after the POB start date.
Cause:
This error typically occurs in the context of contract management or project management within SAP, particularly when dealing with financial agreements or project objects. The specific causes can include:
- Incorrect Date Entry: The freeze date has been entered incorrectly and is set before the POB start date.
- Data Migration Issues: If data has been migrated from another system, there may be inconsistencies in the date entries.
- System Configuration: There may be configuration settings that enforce this rule, and the dates entered do not comply with these settings.
Solution:
To resolve this error, you can take the following steps:
- Check Dates: Review the freeze date and the POB start date. Ensure that the freeze date is indeed set after the POB start date.
- Update Freeze Date: If the freeze date is incorrect, update it to a date that is after the POB start date.
- Review Data Entry: If this error occurs during data entry, ensure that the correct dates are being inputted in the correct format.
- Consult Documentation: If you are unsure about the correct dates, consult the project documentation or the relevant stakeholders to confirm the appropriate dates.
- System Configuration: If you suspect that the error is due to system configuration, consult with your SAP Basis or configuration team to ensure that the settings are correct and align with business rules.
Related Information:
CJ20N
(Project Builder) or FARR
(Contract Management).By following these steps, you should be able to resolve the error and ensure that the freeze date is correctly set in relation to the POB start date.
Get instant SAP help. Sign up for our Free Essentials Plan.
FARR_CONTR_LIFECYCLE094
POB &1: Freeze date &2 must not be after the original POB end date &3.
What causes this issue? POB &v1&: Freeze date &v2& must not be after the original end date &v3& of the Performance Obligation...
FARR_CONTR_LIFECYCLE093
POB &1: Total invoiced amount cannot be positive.
What causes this issue? The transaction price &v2& of the Performance Obligation (POB) is negative. The current invoiced amount and the amoun...
FARR_CONTR_LIFECYCLE096
POB &1: Unfreeze date &2 must be before the POB end date &3.
What causes this issue? POB &v1&: Unfreeze date &v2& must be before POB end date &v3&. Adjust the freeze period &v4&....
FARR_CONTR_LIFECYCLE097
POB &1: Unfreeze date &2 must be after the freeze date &3.
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...