Do you have any question about this error?
Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 072
Message text: Project element '&1' cannot be moved to a project
You want to move a project element of type &V1&. The parent of the
source is a phase or a checklist. The parent of the target is the
project definition. This is not permitted.
The system does not move the project element.
You can only move a project element if the parent of the source and the
parent of the target are on the same level.
Example:
You can move a task below a phase to the same phase or another phase.
You can move a task below a checklist item to a phase, another checklist
item of the same checklist, or another checklist.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED072
- Project element '&1' cannot be moved to a project ?The SAP error message DPR_SHARED072 indicates that a specific project element (such as a task or a work package) cannot be moved to a project. This error typically arises in the context of SAP Project System (PS) or SAP Portfolio and Project Management (PPM) when there are issues related to the project structure or the status of the project element.
Causes:
- Incorrect Project Status: The project or project element may be in a status that does not allow for changes, such as being locked or completed.
- Hierarchy Issues: The project element may not fit into the hierarchy of the target project due to structural constraints.
- Dependencies: There may be dependencies or relationships that prevent the project element from being moved.
- Authorization Issues: The user may not have the necessary authorizations to perform the move operation.
- Inconsistent Data: There may be inconsistencies in the data related to the project or project element.
Solutions:
- Check Project Status: Ensure that the project and the project element are in a status that allows for movement. If the project is completed or locked, you may need to change its status.
- Review Hierarchy: Verify that the project element can logically fit into the target project’s structure. You may need to adjust the hierarchy or choose a different target project.
- Check Dependencies: Look for any dependencies or relationships that might be preventing the move. Resolve any issues before attempting to move the project element again.
- Authorization Check: Ensure that you have the necessary permissions to move project elements. If not, contact your system administrator to obtain the required authorizations.
- Data Consistency: Run consistency checks on the project and project element data to identify and resolve any inconsistencies.
Related Information:
CJ20N
(Project Builder) or CJ02
(Change Project) to review and manage project elements.If the issue persists after checking the above points, it may be beneficial to consult with your SAP support team or refer to SAP community forums for further assistance.
Get instant SAP help. Start your 7-day free trial now.
DPR_SHARED071
Project element of the project cannot be copied to a &1
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
DPR_SHARED070
Project element '&1' cannot be copied to a project
What causes this issue? You want to copy a project element of type &V1&. The parent of the source is a phase or a checklist. The parent of th...
DPR_SHARED073
Project element of project cannot be moved to a &1
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
DPR_SHARED074
&1 is assigned to &2 in Customizing; action is not possible
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...