Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 751
Message text: Order & operation/phase & second. resource &: No rem. avail. cap. avail.
The system could not find any available capacity within the planning
period.
Increase the size of the planning period or
increase the available capacity &V4& or
reschedule a capacity commitment that already exists for the capacity
&V4&
check whether the formulas in the work center for calculating the
duration or capacity requirements lead to diffrent results.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
For example, if the capacity requirements calculated are twice as largeError message extract from SAP system. Copyright SAP SE.
CY751
- Order & operation/phase & second. resource &: No rem. avail. cap. avail. ?The SAP error message CY751 indicates that there is no remaining available capacity for the specified order, operation/phase, and resource. This typically occurs in the context of production planning and scheduling when the system is unable to allocate the required resources to a specific operation due to capacity constraints. Causes: Capacity Overload: The resource (machine, labor, etc.) is already fully booked with other orders or operations, leading to no available capacity for the new order. Incorrect Capacity Planning: The capacity settings for the resource may not be configured correctly, leading to discrepancies in available capacity. Scheduling Conflicts: There may be overlapping operations or phases that are scheduled for the same resource at the same time. Resource Availability: The resource may be marked as unavailable due to maintenance, breakdowns, or other reasons. Incorrect Order Data: The order may have incorrect data regarding the required capacity or operation times. Solutions: Check Resource Availability: Review the capacity planning for the resource
Get instant SAP help. Sign up for our Free Essentials Plan.
CY750
Order & operation &: Rescheduling not permitted because of status
What causes this issue? You want to reschedule an operation. A system- or user status has been set that prevents this action.System Response How to f...
CY749
Order & operation &: Finish date limit exceeded
What causes this issue? Once the operation has been dispatched the finish date constraint is violated. Possible causes include: The constaint date fa...
CY752
Split & person/individual capacity &: Scheduling error
What causes this issue? You have dispatched or rescheduled an operation that has a capacity split. When scheduling split &V1& to the person o...
CY753
Order &: Scheduling not possible
What causes this issue? You are trying to dispatch an operation from an order that has relationships to other orders or is part of a collective order...
Click on this link to search all SAP messages.