How To Fix CY704 - Order & operation & finishes before end of a predecessor


SAP Error Message - Details

  • Message type: E = Error

  • Message class: CY - Capacity Requirements Planning

  • Message number: 704

  • Message text: Order & operation & finishes before end of a predecessor

  • Show details Hide details


  • Self-Explanatory Message

    Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.

    To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.

    Unfortunately, there isn't any extra information in this error notice.



    What else can you do?

    First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).

    Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.

    You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.


Smart SAP Assistant

  • What is the cause and solution for SAP error message CY704 - Order & operation & finishes before end of a predecessor ?

    The SAP error message CY704 ("Order & operation & finishes before end of a predecessor") typically occurs in the context of production planning and scheduling within SAP's PP (Production Planning) module. This error indicates that a specific operation in a production order is scheduled to finish before the predecessor operation has completed. This can lead to scheduling conflicts and inefficiencies in the production process.

    Cause:

    1. Incorrect Scheduling: The operation's finish date is set to occur before the predecessor operation's finish date.
    2. Dependencies Not Respected: The system is unable to respect the defined dependencies between operations, which may be due to incorrect setup in the routing or production order.
    3. Lead Times: The lead times defined for operations may not be sufficient, causing operations to overlap incorrectly.
    4. Manual Changes: Manual adjustments to the scheduling of operations may have inadvertently created conflicts.

    Solution:

    1. Check Routing: Review the routing for the production order to ensure that the sequence of operations is correct and that the dependencies are properly defined.
    2. Adjust Scheduling: Modify the scheduling of the operations to ensure that all predecessor operations finish before the subsequent operations start. This can be done in the production order or through the scheduling settings.
    3. Review Lead Times: Ensure that the lead times for operations are set correctly. Adjust them if necessary to allow for proper sequencing.
    4. Use Scheduling Tools: Utilize SAP's scheduling tools (like the Capacity Planning or Production Planning tools) to automatically adjust the scheduling of operations based on the defined dependencies.
    5. Check for Conflicts: Look for any other production orders or operations that may be causing conflicts in the scheduling and resolve them accordingly.

    Related Information:

    • Transaction Codes: You may use transaction codes like CO02 (Change Production Order) or CO03 (Display Production Order) to review and adjust the production order details.
    • Routing and Work Center: Ensure that the routing and work center settings are correctly configured to reflect the actual production process.
    • SAP Notes: Check for any relevant SAP Notes or documentation that may provide additional insights or fixes related to this error.
    • Testing: After making adjustments, test the changes in a development or quality environment before applying them to the production environment to ensure that the issue is resolved without introducing new problems.

    By following these steps, you should be able to identify the root cause of the CY704 error and implement a solution to resolve it.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant