Do you have any question about this error?
Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 680
Message text: & for requirements grouping & & not found.
In the context of the line representation selection the system looked
for a data record but failed to find it.
The system continues the selection and the current decision step is
treated as an invalid condition.
This can result in lines not being displayed as expected.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
You should check customizing and change it, if necessary.
Error message extract from SAP system. Copyright SAP SE.
CY680
- & for requirements grouping & & not found. ?The SAP error message CY680 typically relates to issues with requirements grouping in the context of production planning and control. This error can occur when the system is unable to find a specific requirements grouping that is necessary for processing a particular transaction or operation.
Cause of Error CY680
- Missing Requirements Grouping: The most common cause is that the requirements grouping specified in the configuration or transaction does not exist in the system.
- Incorrect Configuration: The requirements grouping may not be properly configured in the system, leading to the error.
- Data Inconsistency: There may be inconsistencies in the master data or configuration settings that prevent the system from recognizing the requirements grouping.
- Authorization Issues: Sometimes, the user may not have the necessary authorizations to access the requirements grouping.
Solution
- Check Requirements Grouping: Verify that the requirements grouping you are trying to use exists in the system. You can do this by navigating to the relevant configuration settings in SAP.
- Create or Modify Requirements Grouping: If the requirements grouping does not exist, you may need to create it. This can typically be done in the configuration settings under Production Planning (PP) or Material Management (MM).
- Review Configuration Settings: Ensure that the configuration settings related to requirements grouping are correctly set up. This includes checking the settings in the relevant customizing transactions (e.g., SPRO).
- Check Master Data: Review the master data for the materials or production orders involved to ensure that they are correctly linked to the requirements grouping.
- Authorization Check: Ensure that the user has the necessary authorizations to access and use the requirements grouping.
Related Information
SPRO
(to access the configuration settings) or MD04
(to check the stock/requirements list) to troubleshoot the issue.If the issue persists after following these steps, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in production planning and control.
Get instant SAP help. Start your 7-day free trial now.
CY679
Graphic object type: & index & is not valid.
What causes this issue? The entry in the graphical object type refers to a field in the internal database structure that is not defined.System Respon...
CY678
Graph.obj.type selection: status & sequence & cannot be checked.
What causes this issue? In the graphical object selection a field was entered from the database structure that is not valid.System Response The deci...
CY681
& for capacity requirements & & & not found.
What causes this issue? In the context of the graphical object type selection or the representation selection the system looked for a data record (pe...
CY682
Chart profile & not found
What causes this issue? The chart profile &V1& could not be found.System Response The system cannot set up the planning table. The system st...
Click on this link to search all SAP messages.