How To Fix CY343 - Network &/&: The start date is before the constraint date


SAP Error Message - Details

  • Message type: E = Error

  • Message class: CY - Capacity Requirements Planning

  • Message number: 343

  • Message text: Network &/&: The start date is before the constraint date

  • Show details Hide details
  • What causes this issue?

    The start date for the operation has the constraint that it should not
    be before a particular date (constraint date). However the date when
    you want to dispatch the operation is not before the constraint date.
    Therefore it is not possible to dispatch the operation.

    How to fix this error?

    You should enter a date which is before the constraint date in the
    network.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message CY343 - Network &/&: The start date is before the constraint date ?

    The SAP error message CY343 ("Network &/&: The start date is before the constraint date") typically occurs in the context of project management and scheduling within SAP, particularly when working with networks in the Project System (PS) module or in Production Planning (PP). This error indicates that there is a scheduling conflict where the start date of a network activity is set to begin before a defined constraint date, which is not allowed.

    Cause:

    1. Constraint Date: The constraint date is a date that restricts when an activity can start or finish. This could be due to dependencies on other activities, resource availability, or other scheduling rules.
    2. Incorrect Dates: The start date of the network activity has been incorrectly set to a date that is earlier than the constraint date.
    3. Dependencies: There may be dependencies or relationships between activities that have not been properly defined, leading to scheduling conflicts.
    4. Manual Entry Errors: Users may have manually entered dates that do not comply with the defined constraints.

    Solution:

    1. Check Dates: Review the start date of the network activity and compare it with the constraint date. Adjust the start date to ensure it is on or after the constraint date.
    2. Review Constraints: Examine the constraints set on the network activity. If the constraint is too restrictive, consider adjusting it if it aligns with project requirements.
    3. Adjust Dependencies: If there are dependencies between activities, ensure that they are correctly defined and that the scheduling logic is sound.
    4. Use Scheduling Tools: Utilize SAP's scheduling tools to automatically calculate and adjust dates based on constraints and dependencies.
    5. Consult Documentation: Refer to SAP documentation or help resources for guidance on managing network activities and constraints.

    Related Information:

    • Transaction Codes: You may use transaction codes like CJ20N (Project Builder) or CNO1 (Network Overview) to view and edit network activities.
    • SAP Notes: Check for any relevant SAP Notes that may address specific issues or bugs related to this error message.
    • User Roles: Ensure that users have the appropriate roles and permissions to make changes to network activities and constraints.
    • Training: Consider providing training for users on how to manage project scheduling and constraints effectively within SAP.

    By following these steps, you should be able to resolve the CY343 error and ensure that your project scheduling aligns with the defined constraints.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author