Do you have any question about this error?
Message type: E = Error
Message class: CX_MSR_TRC - Message texts in mult-step returns controller
Message number: 108
Message text: BOM determination failed
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
CX_MSR_TRC108
- BOM determination failed ?The SAP error message CX_MSR_TRC108, which indicates that "BOM determination failed," typically occurs during the process of determining a Bill of Materials (BOM) in the context of production planning or material requirements planning. This error can arise due to various reasons, and understanding the cause is essential for finding a solution.
Causes of CX_MSR_TRC108
Missing BOM: The most common cause is that the system cannot find a valid BOM for the material in question. This could be due to the BOM not being created or not being valid for the specific plant or production version.
Incorrect Material Master Data: If the material master data is incomplete or incorrect, it can lead to issues in BOM determination. This includes missing or incorrect views in the material master.
BOM Status: The BOM might be inactive or not valid for the required period. BOMs can have validity dates, and if the current date falls outside this range, the system will not be able to use it.
Configuration Issues: There may be configuration issues in the system related to BOM determination, such as incorrect settings in the configuration of the material type or BOM usage.
Plant-Specific Settings: The BOM may not be assigned to the specific plant or storage location where the material is being processed.
Versioning Issues: If multiple versions of a BOM exist, the system may not be able to determine which version to use based on the current settings.
Solutions to CX_MSR_TRC108
Check BOM Existence: Verify that a BOM exists for the material in the relevant plant. You can do this using transaction code CS03 (Display BOM).
Review Material Master Data: Ensure that the material master data is complete and correct. Check all relevant views, especially the Basic Data and MRP views.
Validate BOM Status: Check the status of the BOM to ensure it is active and valid for the required period. You can do this in the BOM display transaction.
Configuration Review: Review the configuration settings related to BOM determination. This may involve checking the settings in the material type configuration or BOM usage settings.
Plant Assignment: Ensure that the BOM is assigned to the correct plant and that the plant-specific settings are correct.
Check for Versioning: If multiple BOM versions exist, ensure that the correct version is being referenced in the production order or planning run.
Debugging: If the issue persists, consider debugging the process to identify where the determination is failing. This may require technical expertise.
Related Information
Transaction Codes:
SAP Notes: Check for any relevant SAP Notes that may address known issues or provide patches related to BOM determination.
Documentation: Review SAP documentation related to BOM management and material requirements planning for best practices and troubleshooting tips.
If the issue continues after following these steps, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in production planning and BOM management.
Get instant SAP help. Start your 7-day free trial now.
CX_MSR_TRC107
Replacement material, quantity, and supplying plant have been defaulted
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CX_MSR_TRC106
Enter a supplying plant
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CX_MSR_TRC109
Replacement material cannot be a BOM
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CX_MSR_TRC110
Enter a replacement material
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...