How To Fix CNV_DMC_SIN537 - Costing of WorkCenter/plant &1/&2 begins after operation start on date &3


SAP Error Message - Details

  • Message type: E = Error

  • Message class: CNV_DMC_SIN - Messages for s-innovations migration

  • Message number: 537

  • Message text: Costing of WorkCenter/plant &1/&2 begins after operation start on date &3

  • Show details Hide details


  • Self-Explanatory Message

    Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.

    To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.

    Unfortunately, there isn't any extra information in this error notice.



    What else can you do?

    First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).

    Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.

    You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.


Smart SAP Assistant

  • What is the cause and solution for SAP error message CNV_DMC_SIN537 - Costing of WorkCenter/plant &1/&2 begins after operation start on date &3 ?

    The SAP error message CNV_DMC_SIN537 indicates that there is an issue with the costing of a work center in relation to a specific operation. The message states that the costing for the work center/plant combination begins after the operation's start date, which can lead to inconsistencies in the costing calculations.

    Cause:

    1. Costing Start Date: The primary cause of this error is that the costing for the work center is not set up to start before or on the operation's start date. This can happen if the work center's cost planning is not aligned with the production scheduling.
    2. Configuration Issues: There may be configuration issues in the work center or plant settings that prevent the costing from being applied correctly.
    3. Data Migration Issues: If this error arises during a data migration process (as suggested by the prefix CNV_DMC), it could be due to incorrect or incomplete data being transferred.

    Solution:

    1. Adjust Costing Dates: Review the costing settings for the work center and ensure that the costing starts on or before the operation's start date. You can do this by:

      • Navigating to the work center configuration in SAP (Transaction code: CR01/CR02).
      • Checking the "Costing" tab and adjusting the "Costing Start Date" accordingly.
    2. Review Work Center Configuration: Ensure that the work center is properly configured with the correct costing information. This includes checking:

      • Validity periods for cost rates.
      • Any planned costs associated with the work center.
    3. Check Production Order: If this error is related to a specific production order, check the order's scheduling and ensure that the operations are correctly defined with respect to the work center's costing.

    4. Data Migration Review: If this error occurs during a data migration process, review the migration data to ensure that all necessary costing information is included and correctly formatted.

    5. Consult Documentation: Refer to SAP documentation or notes related to this specific error message for additional guidance and troubleshooting steps.

    Related Information:

    • Transaction Codes:
      • CR01/CR02: Create/Change Work Center
      • CO01/CO02: Create/Change Production Order
    • SAP Notes: Check for any relevant SAP Notes that may address this specific error or provide additional context.
    • Costing Configuration: Familiarize yourself with the costing configuration in SAP, including how to set up cost centers, work centers, and their associated cost rates.

    If the issue persists after following these steps, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in production planning and costing.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant