Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 852
Message text: Activity loses its internal processing character
You have changed the control key of the activity. The new control key
specifies that the activity is externally processed.
The activity will be displayed on the overview for externally processed
activities.
Error message extract from SAP system. Copyright SAP SE.
The SAP error message CN852 ("Activity loses its internal processing character") typically occurs in the context of project management and controlling within SAP, particularly when dealing with activities in a project structure. This error indicates that an activity is being changed in a way that affects its internal processing character, which can lead to inconsistencies in project planning and execution.
Cause:
The error can arise due to several reasons, including:
Change in Activity Type: If an activity is changed from a type that allows certain processing (like a work activity) to a type that does not (like a milestone), it can trigger this error.
Inconsistent Data: If there are inconsistencies in the data related to the activity, such as incorrect settings or parameters that do not align with the expected processing character.
Project Structure Changes: Modifications in the project structure that affect the hierarchy or relationships between activities can also lead to this error.
Status Changes:
Get instant SAP help. Sign up for our Free Essentials Plan.
CN851 Minimum duration must not exceed standard duration
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN850 ======== Standard network/network-specific messages =====================
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN853 Activity loses its external processing character
What causes this issue? You have changed the control key of the activity. The new control key specifies that the activity is internally processed.Sys...
CN854 You can only enter a cost control key
What causes this issue? You have entered a control key for this activity that is not valid for general costs activities.System Response INCLUDE ...