Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 844
Message text: Company code activity & and WBS element & are not identical
You have changed the company code of the activity by changing the plant.
A material component kept in either sales order stock or project stock
is allocated to this activity. This means that the component quantity
is tracked in the project stock for the WBS element to which the
activity is assigned. The component value is tracked in the activity.
The business areas of the activity and the WBS element must agree so
that the business area balances which the company code requires can be
created.
&WHAT_TO_DO_&
Reverse your entries.
Error message extract from SAP system. Copyright SAP SE.
CN844
- Company code activity & and WBS element & are not identical ?The SAP error message CN844 indicates that there is a mismatch between the company code associated with a particular activity and the WBS (Work Breakdown Structure) element in a project. This error typically arises when you are trying to assign costs or perform transactions that involve both the activity and the WBS element, but they belong to different company codes.
Cause:
- Different Company Codes: The most common cause of this error is that the activity and the WBS element are defined in different company codes. Each company code in SAP is treated as a separate legal entity, and transactions involving different company codes cannot be processed together.
- Incorrect Configuration: There may be configuration issues in the project system or the controlling module that lead to this mismatch.
- Data Entry Errors: Manual entry errors when assigning activities or WBS elements can also lead to this issue.
Solution:
Verify Company Codes: Check the company code assigned to both the activity and the WBS element. Ensure that they are the same. You can do this by navigating to the relevant transaction codes:
- For WBS elements, use transaction code CJ03 (Display WBS Element).
- For activities, use transaction code CJ20N (Project Builder) or CJR2 (Display Activity).
Change Company Code: If you find that they are indeed different, you will need to either:
- Change the company code of the activity or WBS element to match the other.
- Create a new activity or WBS element in the correct company code if changing is not feasible.
Check Project Structure: Ensure that the project structure is correctly set up and that all elements are aligned under the same company code.
Consult Configuration: If the issue persists, consult with your SAP configuration team to ensure that the project system settings are correctly configured to allow for the intended transactions.
Review Authorization: Ensure that you have the necessary authorizations to perform the actions you are attempting, as sometimes authorization issues can lead to misleading error messages.
Related Information:
By following these steps, you should be able to resolve the CN844 error and ensure that your project activities and WBS elements are correctly aligned within the same company code.
Get instant SAP help. Start your 7-day free trial now.
CN843
Business areas activity & and WBS element & are not identical
What causes this issue? You have changed the business area of the activity.System Response A material component kept in either sales order stock or ...
CN842
Company code & requires a business area
What causes this issue? In Customizing for financial accounting, you have defined that for company code &V1& a balance sheet or P&L state...
CN845
Relationships were created
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN846
You cannot create because network & is not locked
What causes this issue? You attempted to create an activity in network &V1& which is not locked by using the insert or copy function.System R...
Click on this link to search all SAP messages.