Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 838
Message text: Several start/target activities exist
The network which is to become a subnetwork has several start and/or
finish (target) activities.
In this situation, the system creates relationships to all start and/or
finish (target) activities.
INCLUDE 'NA_ALLG_FUNKTION' OBJECT DOKU ID TX
Error message extract from SAP system. Copyright SAP SE.
CN838
- Several start/target activities exist ?The SAP error message CN838 ("Several start/target activities exist") typically occurs in the context of project management within SAP, particularly when dealing with network activities in Project System (PS). This error indicates that there are multiple activities that are defined as either start or target activities for a given network, which can lead to ambiguity in scheduling and planning.
Cause:
- Multiple Start Activities: The network may have more than one activity defined as a start activity, which confuses the system about which activity should be the actual starting point.
- Multiple Target Activities: Similarly, if there are multiple target activities defined, the system cannot determine which one should be the endpoint of the network.
- Incorrect Network Configuration: The network structure may not be configured correctly, leading to overlapping or conflicting definitions of activities.
Solution:
- Review Network Activities: Go to the network in question and review the activities defined. Ensure that there is only one start activity and one target activity.
- Adjust Activity Settings: If you find multiple start or target activities, you will need to adjust the settings:
- Change Activity Type: If an activity is incorrectly marked as a start or target activity, change its type accordingly.
- Delete or Merge Activities: If there are redundant activities, consider deleting or merging them to simplify the network structure.
- Check Dependencies: Ensure that the dependencies between activities are correctly defined. This includes checking for any constraints that may lead to multiple start or target activities.
- Recreate the Network: In some cases, if the network is too complex or incorrectly set up, it may be easier to recreate the network from scratch with the correct definitions.
Related Information:
CN21
(Create Network), CN22
(Change Network), and CN03
(Display Network) to manage network activities.By following these steps, you should be able to resolve the CN838 error and ensure that your project network is correctly configured.
Get instant SAP help. Start your 7-day free trial now.
CN837
Relationships betw. activities in different alternatives are not allowed
What causes this issue? You have entered a relationship to another alternative of the standard network. This is not allowed.System Response INCLUDE ...
CN836
Duration cannot be converted into desired unit
What causes this issue? You have selected different units for work and duration when calculating duration. In this case, the calculated value for dur...
CN839
Start and target activities cannot be identical
What causes this issue? You have entered the same activity number for both the beginning and target activities. When you include this standard networ...
CN840
Relationship is being processed with change number &
What causes this issue? The relationship has already been edited with change number &V1&. In this situation, you cannot delete the relationsh...
Click on this link to search all SAP messages.