Do you have any question about this error?
Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 820
Message text: No work center assigned to predecessor
You want to calculate the time interval of the relationship as a
percentage of the duration of the predecessor. But no work center has
been entered for this activity and therefore no calendar is available
to perform this calculation.
The function is carried out. If you have not entered a work center for
the predecessor, the system uses the factory calendar to calculate the
time interval that you have maintained in the network header or the
header of the standard network.
Error message extract from SAP system. Copyright SAP SE.
CN820
- No work center assigned to predecessor ?The SAP error message CN820 ("No work center assigned to predecessor") typically occurs in the context of project management and production planning when there is an issue with the assignment of work centers in a network or activity within a project. This error indicates that the predecessor activity does not have a work center assigned, which is necessary for scheduling and resource allocation.
Cause:
- Missing Work Center Assignment: The predecessor activity in the project network does not have a work center assigned to it. This can happen if the activity was created without specifying a work center or if the work center was deleted or not properly configured.
- Incorrect Configuration: The work center may not be correctly set up in the system, or it may not be valid for the type of activity being processed.
- Data Inconsistencies: There may be inconsistencies in the data related to the project or network, such as missing or incorrect links between activities and work centers.
Solution:
Assign a Work Center:
- Go to the project or network activity where the error occurred.
- Check the details of the predecessor activity.
- Assign a valid work center to the predecessor activity. This can usually be done in the activity details screen under the "Basic Data" or "Work Center" tab.
Check Work Center Configuration:
- Ensure that the work center you are trying to assign is correctly configured in the system.
- Verify that the work center is active and has the necessary parameters set up (e.g., capacity, cost center).
Review Project Structure:
- Check the overall structure of the project or network to ensure that all activities and their relationships are correctly defined.
- Make sure that all predecessor and successor relationships are properly established.
Data Consistency Check:
- Run a consistency check on the project or network to identify any other potential issues that may be causing the error.
- Use transaction codes like CN22 (for network activities) or CN41 (for project structure) to review and correct any inconsistencies.
Consult Documentation:
- Refer to SAP documentation or help resources for additional guidance on managing work centers and project activities.
Related Information:
By following these steps, you should be able to resolve the CN820 error and ensure that your project activities are properly configured for scheduling and resource allocation.
Get instant SAP help. Start your 7-day free trial now.
CN819
No work center assigned to successor
What causes this issue? You want to calculate the time interval of the relationship as a percentage of the duration of the successor. But no work cen...
CN818
Relationships cannot be maintained
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN821
This relationship already exists
What causes this issue? You have maintained a relationship that already exists.System Response INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOK...
CN822
Error in determining work center for relationship
What causes this issue? An internal error occurred when attempting to determine the work center assigned to the relationship.System Response INCLUDE...
Click on this link to search all SAP messages.