Do you have any question about this error?
Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 287
Message text: Component & is not intended for monitoring dates
You have not made all the settings necessary for monitoring dates of
this component. You first define at least one group for the project and
assign events and components to the group. The events must be have been
previously defined in Customizing.
&FURTHER_HINTS&
For more information, refer to the SAP Library under Project System ->
Material -> Monitoring Dates
Error message extract from SAP system. Copyright SAP SE.
CN287
- Component & is not intended for monitoring dates ?The SAP error message CN287 typically indicates that a specific component in a project or network is not set up for monitoring dates. This can occur in the context of project management or network planning within SAP, particularly in the Project System (PS) module.
Cause:
The error message CN287 arises when:
- Component Configuration: The component in question is not configured to allow for date monitoring. This could be due to settings in the project definition or network activities.
- Project Type: The project type or the settings associated with it may not support date monitoring for the specified component.
- Missing Parameters: Required parameters for monitoring dates may not be set up correctly in the project or network.
Solution:
To resolve the CN287 error, you can take the following steps:
Check Component Settings:
- Navigate to the project or network in question and check the settings for the specific component.
- Ensure that the component is configured to allow for date monitoring.
Review Project Type:
- Verify that the project type supports date monitoring. If it does not, you may need to change the project type or adjust the settings accordingly.
Adjust Monitoring Parameters:
- Go to the project definition or network activity and check the parameters related to date monitoring.
- Ensure that all necessary fields are filled out and that the component is included in the monitoring setup.
Consult Documentation:
- Refer to SAP documentation or help resources for specific guidance on configuring components for date monitoring.
SAP Notes and Support:
- Check for any relevant SAP Notes that may address this issue. Sometimes, there are known issues or patches that can resolve specific error messages.
- If the problem persists, consider reaching out to SAP support for further assistance.
Related Information:
By following these steps, you should be able to identify the cause of the CN287 error and implement a solution to enable date monitoring for the specified component.
Get instant SAP help. Start your 7-day free trial now.
CN286
Enter a project, WBS element, or network
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CN285
No component could be determined with the selection criteria
What causes this issue? You want to call up Monitoring Dates for the components in a project, one or more WBS elements, or in a network.System Respon...
CN288
Network type &1 plant &2: No checking rule maintained for activity
What causes this issue? A checking rule must be maintained in order to carry out a material availability check. However, no checking rule has been ma...
CN289
All inspected material components available for network &
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.