Message type: E = Error
Message class: CK - Product Costing Messages
Message number: 879
Message text: Own costs transferred with direct partner &1
The partner cost component split of direct partner &V1& contains costs
that arose at that direct partner. This is not allowed.
NOTE FOR TRANSLATOR: "Eigenanteil" means costs that arose at the
organizational unit in question, rather than at the partners.
Example
The header material is in plant 1000. The table of the cost component
split of the direct partner <ZK>plant</> contains costs from plant
1000. This is not allowed.
It is not possible to create a cost component split.
Check the data.
Error message extract from SAP system. Copyright SAP SE.
CK879
- Own costs transferred with direct partner &1 ?The SAP error message CK879, which states "Own costs transferred with direct partner &1," typically occurs in the context of cost accounting and controlling when there is an issue with the transfer of costs between different cost centers or profit centers. This error can arise in various scenarios, such as during the execution of cost allocation processes or when posting costs to a specific partner.
Cause: The error CK879 can be caused by several factors, including: Incorrect Configuration: The configuration of cost centers, profit centers, or internal orders may not be set up correctly, leading to issues in cost allocation. Missing Master Data: The necessary master data for the partner (e.g., cost center or internal order) may be missing or incorrectly maintained. Posting Errors: There may be errors in the posting logic, such as incorrect account assignments or missing entries in the relevant tables. Direct Partner Assignment: The system may be trying to transfer costs to
Get instant SAP help. Sign up for our Free Essentials Plan.
CK878
Fill either COSTESTIM_ID or ORG_MEASURE
What causes this issue? Either parameter COSTESTIM_ID or parameter ORG_MEASURE must be filled. If COSTESTIM_ID is filled, the cost estimate that is t...
CK877
Sales order costing not possible for recursive configurable materials
What causes this issue? The system recognized that the BOM structure being costed is a recursive production process in which configurable materials a...
CK880
Cost comp. split does not match partner split at comp. &1
What causes this issue? For cost component &V1& the data of the cost component split does not match the partner cost component split in the f...
CK881
Own costs less than zero with direct partner &1, component &2
What causes this issue? The cost share for direct partner &V1& in cost component &V2& is less than zero. The direct partner's co...