Do you have any question about this error?
Message type: E = Error
Message class: CK - Product Costing Messages
Message number: 472
Message text: Material & in plant & is not relevant for costing with qty structure
You are attempting to cost the material &V1& in plant &V2& using sales
order costing. The settings for this material contradict each other:
The <DS:DE.CK_EKALREL>With quantity structure</> indicator in the
costing view of the material master record is not set.
In the MRP 1 view in the material master record, the MRP group points
to a requirements class that specifies that the material is to be
costed in a <DS:GLOS.cost_estimate_with_quantity_structure>cost
estimate with quantity structure</>.
The system uses the price in the material's master record.
The planned costs for this material go into the cost estimate as raw
material costs.
If you always want to cost this material in a cost estimate with
quantity sturcture, set the <LS>With quantity structure</> indicator in
the material's master record.
<DS:TRAN.MM02>Change material master record</>
If you normally want to cost this material in a unit cost estimate,
change the requirements class. You have two options here:
You can change the MRP group in the MRP 1 view in the material's master
record.
<DS:TRAN.MM02>Change material master record</>
You can change the settings in Customizing for the requirements class
that is entered with the MRP group in the MRP 1 view in the material's
master record.
<DS:TRAN.MM03>Change material master record</>
Error message extract from SAP system. Copyright SAP SE.
CK472
- Material & in plant & is not relevant for costing with qty structure ?The SAP error message CK472 indicates that a specific material in a particular plant is not relevant for costing with quantity structure. This typically occurs during the costing process when the system attempts to calculate the cost of a material that has not been set up correctly for costing purposes.
Cause:
- Material Master Settings: The material may not be marked as relevant for costing in the material master record. This can happen if the costing view is not maintained or if the material type does not allow for costing.
- Plant Settings: The plant settings for the material may not be configured to allow for costing. This can include settings related to valuation, costing variants, or other related configurations.
- Quantity Structure: The material may not have a quantity structure defined, which is necessary for the costing process. This can occur if the material is not set up for production or if it is a non-stock material.
- Costing Variant: The costing variant used may not be appropriate for the material or plant in question.
Solution:
Check Material Master:
- Go to the material master record (transaction code MM03) and check the costing view. Ensure that the material is marked as relevant for costing.
- Verify that the material type allows for costing and that the necessary views are maintained.
Review Plant Settings:
- Check the plant-specific settings for the material. Ensure that the valuation area is correctly set up and that the material is assigned to the correct valuation class.
Define Quantity Structure:
- If the material is intended for production, ensure that it has a BOM (Bill of Materials) and routing defined. This is necessary for the system to create a quantity structure for costing.
- If the material is a non-stock item, consider whether it should be included in the costing process.
Costing Variant Configuration:
- Review the costing variant being used in the costing run. Ensure that it is configured correctly and is applicable to the material and plant in question.
Consult Documentation:
- Refer to SAP documentation or help resources for further details on the specific error message and related configuration settings.
Related Information:
Transaction Codes:
Material Types: Different material types in SAP have different settings and implications for costing. Ensure that the material type is appropriate for your costing needs.
Costing Views: Ensure that the costing views in the material master are properly maintained, including the standard price or moving average price.
SAP Notes: Check for any relevant SAP Notes that may address specific issues related to this error message.
By following these steps, you should be able to identify the cause of the CK472 error and implement the necessary changes to resolve it.
Get instant SAP help. Start your 7-day free trial now.
CK471
Material & in plant & is not relevant for costing with qty structure
What causes this issue? You are attempting to cost material &V1& in plant &V2& using sales order costing. The <DS:DE.CK_EKALREL>...
CK470
The selected materials will not be updated
What causes this issue? You are attempting to <DS:GLOS.3526B6E6AFAB52B9E10000009B38F974>update</> the results of one or more cost estimat...
CK473
Cost estimate stored in buffer
What causes this issue? The system issues an error message and will not allow you to continue with this transaction until the error is resolved. Syst...
CK474
The costing lot size is smaller than the price unit
What causes this issue? The desired costing lot size is &v1&. This is less than the price unit in the material master (&v2&).System R...
Click on this link to search all SAP messages.