Message type: E = Error
Message class: CK - Product Costing Messages
Message number: 465
Message text: No price could be determined for material/batch &1 plant &2
The system could not calculate a price for material/batch &v1& in plant
&v2& for <DS:GLOS.valuation_view>valuation view</> &V4&, because none
of the <DS:GLOS.valuation_strategy>valuation strategies</> in
<DS:GLOS.valuation_variant>valuation variant</> &v3& was successful.
User-defined error management enables you to specify whether the
message is an error message, a warning message or an information
message.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
If you have defined the message as a <ZH>warning message</> or anCheck the master data for material/batch &v1& in plant &v2&.
If you have authorization for Customizing, check the valuation strategy
for materials in valuation variant &v3&.
<ZH>Note</>
If the message is a warning message or an information message, there is
a danger that materials with errors will be ignored by the system.
If, because of this, you issue a warning message and at the same time
include materials with a zero value in cost estimates, you can make the
following settings for these materials in the costing view of the
material master:
Enter a very low price in the <ZH>planned price 1</>, <ZH>2</> or <ZH>3
</> fields manually, for instance 0.01 USD. These prices are used for
costing purposes only; they are not read by other applications.
Enter the highest price unit possible, for example 10000.
Note: If you enter a new price unit that is higher than the costing lot
size, the system increases the costing lot size accordingly.
Change the valuation strategy, such as strategy 4, where you could
enter the planned price field in which you entered the low price.
The system now costs as follows:
Using the valuation strategy, the system finds planned price 1, 2 or 3.
Due to the low price and high price unit, the system rounds the value
to zero. However, the cost estimate still obtains status KA (free of
errors), and no error message is issued.
This procedure can be used for all materials that have caused error
message CK465 to be issued.
Error message extract from SAP system. Copyright SAP SE.
CK465
- No price could be determined for material/batch &1 plant &2 ?The SAP error message CK465 ("No price could be determined for material/batch &1 plant &2") typically occurs during the costing process when the system is unable to find a valid price for a specific material and batch in a given plant. This can happen for several reasons, and understanding the cause is essential for resolving the issue. Causes: Missing Price Control: The material may not have a price control indicator set (e.g., moving average price or standard price). Batch Management Issues: If the material is batch-managed, the specific batch may not have a price assigned. Material Master Data: The material master data may be incomplete or incorrectly configured, particularly in the accounting view. Valuation Class: The valuation class assigned to the material may not be set up correctly in the configuration. No Valid Price in the Price Determination Process: The system may not find a valid price in the price determination process due to missing or
Get instant SAP help. Sign up for our Free Essentials Plan.
CK464
Lot size for material & in plant & taken from costing view
What causes this issue? In sales order costing, the lot size for individual requirements materials should be determined dynamically. You specified th...
CK463
Pass on lot size function not supported in costing runs
What causes this issue? You have selected costing variant &v1& for the costing run. The <DS:DE.CK_LOSDR>Pass on lot size</> indic...
CK466
No price could be determined for internal activity &1 &2
What causes this issue? The system could not calculate a price for the internal activity with activity type &v1& of cost center &v2& ...
CK467
No price could be determined for external processing
What causes this issue? The system could not calculate a price for external activities because none of the valuation strategies in valuation variant ...