Message type: E = Error
Message class: CK - Product Costing Messages
Message number: 239
Message text: Cost element & is not assigned to a cost component
The system attempted to generate the <DS:GLOS.cost_component_split>cost
component split</> for the material, but discovered that no assignment
has been made in <DS:GLOS.cost_component_structure>cost component
structure</> &V3& for <DS:GLOS.cost_element>cost element</> &V1& and
possibly for origin group &v2&.
The cost component split is incomplete. The
<DS:GLOS.3526B70FAFAB52B9E10000009B38F974>cost of goods manufactured
</> in the cost component split is therefore less than in the
<DS:GLOS.3526B5B5AFAB52B9E10000009B38F974>itemization</>.
Go into Customizing for Product Cost Controlling and carry out the
assignment for cost component structure &V3& and chart of accounts &V4&
.
Error message extract from SAP system. Copyright SAP SE.
CK239
- Cost element & is not assigned to a cost component ?The SAP error message CK239 indicates that a specific cost element is not assigned to a cost component in the context of product costing. This error typically arises during the process of cost calculation or when trying to perform activities related to cost planning, such as creating or changing a cost estimate.
Cause:
The primary cause of the CK239 error is that the cost element specified in the error message has not been linked to any cost component in the cost component structure. Cost components are used in product costing to categorize costs (e.g., material costs, labor costs, overhead costs) and are essential for accurate cost calculations.
Solution:
To resolve the CK239 error, you need to ensure that the cost element is properly assigned to a cost component. Here are the steps to do this:
Access the Cost Component Structure:
- Go to the transaction code OKTZ (Cost Component Structure) in SAP.
Select the Relevant Cost Component Structure:
- Identify and select the cost component structure that is relevant for your costing scenario.
Assign the Cost Element:
- In the cost component structure, check if the cost element mentioned in the error message is listed.
- If it is not listed, you need to add it. You can do this by selecting the appropriate cost component and then assigning the cost element to it.
Save Changes:
- After making the necessary assignments, save your changes.
Re-run the Cost Estimate:
- After assigning the cost element to the cost component, try to re-run the cost estimate or the process that triggered the CK239 error.
Related Information:
By following these steps, you should be able to resolve the CK239 error and ensure that your cost estimates are calculated correctly. If the issue persists, it may be beneficial to consult with your SAP support team or a functional consultant specializing in controlling (CO) and product costing.
Get instant SAP help. Start your 7-day free trial now.
CK238
Plant & is not the only plant assigned to valuation area &
What causes this issue? You are attempting to use material costing or order costing. However, the system has determined that plant &v1& is no...
CK237
No reference object found during number assignment
What causes this issue? A cost estimate must have a key that is unique in the system. This is achieved by saving the costing document under a unique ...
CK240
Cost component split costed with value of zero
What causes this issue? The cost component split can have a value of 0 if the quantity structure is not relevant to costing no valid price could be s...
CK241
Value of cost component split is less than zero
What causes this issue? The <DS:GLOS.cost_of_goods_manufactured>cost of goods manufactured</> of the main product was more than compensat...