How To Fix CJ516 - You cannot delete the finish date


CJ516 - Overview

  • Message type: E = Error

  • Message class: CJ - Project master data and structure

  • Message number: 516

  • Message text: You cannot delete the finish date

  • Show details Hide details
  • What causes this issue?

    The superior WBS element already has an actual finish date. You cannot
    delete this date.

    System Response

    The system automatically uses the old date.

    How to fix this error?

    You can only change the actual dates for a WBS element. You cannot
    delete the dates.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message CJ516 - You cannot delete the finish date ?
    The SAP error message CJ516 ("You cannot delete the finish date") typically occurs in the context of project management within SAP, particularly when dealing with project definitions or work breakdown structures (WBS). This error indicates that the system is preventing the deletion of a finish date for a project or WBS element due to certain constraints or dependencies.
    Causes:
    
    Dependencies: The finish date may be linked to other project elements or activities that have dependencies. Deleting it could disrupt the project schedule.
    Status of the Project: If the project or WBS element is in a status that does not allow changes (e.g., completed or closed), the system will prevent modifications to the finish date.
    Project Planning: The finish date may be part of a planning scenario that requires it to remain intact for reporting or scheduling purposes.
    Authorizations: Lack of proper authorizations to make changes to project data can also lead to this error.
    
    Solutions:
    
    Check Dependencies:

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:
  • CJ515 You cannot delete the start date
    What causes this issue? There are already confirmations for this activity. You can no longer change the actual start date for the WBS element.System ...

  • CJ514 No overlapping dates found
    Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...

  • CJ517 No schedule conflicts found
    Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...

  • CJ518 No activities copied
    Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...

Click on this link to search all SAP messages.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author