Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 194
Message text: You cannot copy an activity milestone to a WBS element
You have tried to paste an activity milestone to a WBS element.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Select an activity and repeat the "Paste" function.
Error message extract from SAP system. Copyright SAP SE.
CJ194
- You cannot copy an activity milestone to a WBS element ?The SAP error message CJ194, which states "You cannot copy an activity milestone to a WBS element," typically occurs when there is an attempt to copy an activity milestone to a Work Breakdown Structure (WBS) element in the Project System (PS) module. This error arises due to the inherent differences in the nature of activities and milestones in project management.
Cause:
Nature of Milestones: Milestones are specific points in time that signify important events or phases in a project, while WBS elements represent the hierarchical structure of the project and its deliverables. Since milestones do not have a duration or resource allocation, they cannot be directly copied to WBS elements.
Incorrect Copying Method: The method used to copy the milestone may not be appropriate for the target object (WBS element). The system expects certain attributes and structures that are not compatible between activities and WBS elements.
Configuration Settings: There may be specific configuration settings in the SAP system that restrict the copying of certain types of objects.
Solution:
Manual Creation: Instead of copying the milestone, manually create a new milestone under the desired WBS element. This ensures that the milestone is correctly associated with the WBS structure.
Use of Project Planning Tools: Utilize project planning tools within SAP that allow for the proper assignment of milestones to WBS elements. This may involve using transaction codes like CJ20N (Project Builder) to manage project structures effectively.
Check Configuration: Review the configuration settings in the Project System to ensure that there are no restrictions on copying or moving milestones. Consult with your SAP administrator or a functional consultant if necessary.
Documentation and Training: Ensure that users are trained on the differences between activities and milestones and the correct procedures for managing them within the SAP system.
Related Information:
By following these steps, you should be able to resolve the CJ194 error and effectively manage your project milestones and WBS elements in SAP.
Get instant SAP help. Sign up for our Free Essentials Plan.
CJ193
Selct one or more project objects of the same type
What causes this issue? Either you have not selected an object or you have selected several types of object. You can only select objects of the same ...
CJ192
WBS element & has no activities
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ195
Open project starts project &1 in the planning board
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ196
&1 cannot be moved to &2
What causes this issue? You have tried to move a &v1& to a &v2&.System Response You cannot change the type of object that a mileston...