Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 116
Message text: Superior WBS element released or technically completed
If the system was to execute the function 'Derive structure', it would
place a WBS element with status released or techically completed above
a WBS element with system status created. This would lead to an
inconsistency of the system statuses within the project hierarchy.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
Error message extract from SAP system. Copyright SAP SE.
CJ116
- Superior WBS element released or technically completed ?The SAP error message CJ116 indicates that the superior Work Breakdown Structure (WBS) element is either released or technically completed. This error typically occurs when you attempt to perform certain actions (like posting costs or creating new activities) on a subordinate WBS element while its parent WBS element is in a status that does not allow such actions.
Cause:
- Superior WBS Element Status: The superior WBS element is either in a "Released" or "Technically Completed" status. This means that it is not open for further transactions, which can include cost postings or changes to its subordinate elements.
- Project Lifecycle: In project management, once a project or a phase is completed, it is common to set the WBS element to a status that prevents further changes to ensure data integrity and accurate reporting.
Solution:
To resolve the CJ116 error, you can take the following steps:
Check the Status of the Superior WBS Element:
- Navigate to the superior WBS element in the SAP system.
- Check its status in the project management transaction (e.g., CJ03 for display, CJ02 for change).
- If it is in "Released" or "Technically Completed" status, you will need to change its status if further transactions are necessary.
Change the Status:
- If you need to continue working on the project, you may need to set the superior WBS element back to a status that allows transactions (e.g., "In Process").
- This can typically be done using transaction CJ02 (Change WBS Element) and adjusting the status accordingly.
Consult with Project Management:
- If the superior WBS element should remain in its current status (e.g., if the project is indeed completed), you may need to review your actions and ensure that you are not trying to post costs or make changes that are not allowed at this stage of the project lifecycle.
Review Project Structure:
- Ensure that the project structure is correctly set up and that you are not inadvertently trying to post to a WBS element that should not be active.
Related Information:
By following these steps, you should be able to resolve the CJ116 error and continue with your project management tasks in SAP.
Get instant SAP help. Sign up for our Free Essentials Plan.
CJ115
Could not find a superior WBS element for WBS element &
What causes this issue? The system could not find a superior element for a WBS element while it was executing the function 'Derive structure...
CJ114
Function cannot be executed, please check
What causes this issue? Errors occurred during execution of the function 'Derive structure - Execute'.How to fix this error? Choose '...
CJ117
WBS element & is assigned to a capital investment measure
What causes this issue? If the system was to execute the function 'Derive structure', it would place a WBS element that is assigned to a ca...
CJ118
No editing mask exists for project &
What causes this issue? The 'Derive structure' function can only be executed, if the project definition and all the WBS elements have a (co...