Do you have any question about this error?
Message type: E = Error
Message class: CI_DRAFTPRD_MESSAGE -
Message number: 100
Message text: Ordering costs require lot size (Products planning)
You have selected ordering costs for copying to the profile. However,
they can only be copied if you also specify a lot size (products
planning) in the profile.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Select the lot size on the selection screen.
Error message extract from SAP system. Copyright SAP SE.
CI_DRAFTPRD_MESSAGE100
- Ordering costs require lot size (Products planning) ?The SAP error message CI_DRAFTPRD_MESSAGE100, which states "Ordering costs require lot size," typically occurs in the context of product planning and material requirements planning (MRP) when there is an issue with the configuration of lot sizes for a material. This error indicates that the system requires a defined lot size for calculating ordering costs, but it is not properly set up.
Cause:
- Missing Lot Size Configuration: The material master record may not have a lot size defined, which is necessary for calculating ordering costs.
- Incorrect MRP Type: The MRP type assigned to the material may not be compatible with the ordering cost calculations.
- Incomplete Master Data: Other related master data, such as the purchasing info record or the BOM (Bill of Materials), may be incomplete or incorrectly configured.
- Lot Size Procedure: The lot size procedure defined in the material master may not be appropriate for the type of planning being performed.
Solution:
Check Material Master Data:
- Go to the material master (transaction code MM03) and check the relevant views (especially the MRP view).
- Ensure that a lot size is defined in the "Lot Size" field. Common lot sizes include "Fixed Lot Size," "Weekly Lot Size," or "Monthly Lot Size."
Review MRP Type:
- Ensure that the MRP type assigned to the material is appropriate for the planning strategy being used. For example, if you are using a lot-for-lot strategy, ensure that it is set correctly.
Update Lot Size Procedure:
- If necessary, update the lot size procedure in the material master to one that is compatible with your planning needs.
Check Related Master Data:
- Review the purchasing info record (transaction code ME13) and ensure that it is correctly set up.
- Check the BOM (transaction code CS03) if applicable, to ensure that it is complete and correctly configured.
Consult Documentation:
- If you are unsure about the appropriate lot size or MRP type, consult SAP documentation or your organization's SAP support team for guidance.
Related Information:
By addressing the above points, you should be able to resolve the CI_DRAFTPRD_MESSAGE100 error and ensure that your material planning processes function correctly. If the issue persists, consider reaching out to your SAP support team for further assistance.
Get instant SAP help. Start your 7-day free trial now.
CI_DRAFTPRD_MESSAGE099
Maximum stock level requires lot size (Products planning)
What causes this issue? You have selected <ZH>Maximum stock level </>for copying to the profile, but it can be copied only if you also sp...
CI_DRAFTPRD_MESSAGE098
Fixed lot size requires lot size (Products planning)
What causes this issue? You have selected <ZH>Fixed lot size</> for copying to the profile, but it can be copied only if you also specif...
CI_DRAFTPRD_MESSAGE101
Storage costs indicator requires lot size (Products planning)
What causes this issue? You have selected the storage costs indicator for copying to the profile. However, it can only be copied if you also specify ...
CI_DRAFTPRD_MESSAGE102
Product forecast is new; enter the initialization indicator
What causes this issue? You want to carry out the first forecast for the product. The first time a forecast is carried out, the initialization indica...