Do you have any question about this error?
Message type: E = Error
Message class: CE - CAPP messages
Message number: 337
Message text: To calculate std. values via CAPP, enter a work center in the op./sub-op.
Standard values for an operation or sub-operation can only be
calculated via CAPP if
a work center has been specified in the operation or sub-operation
at least one process has been assigned to this work center
If the processes and methods to be used for the calculation
are selected automatically, the system ignores operations and
sub-operations for which no work center has been specified.
Specify a work center in the operation or sub-operation or assign a
process to the work center.
Error message extract from SAP system. Copyright SAP SE.
CE337
- To calculate std. values via CAPP, enter a work center in the op./sub-op. ?The SAP error message CE337, which states "To calculate std. values via CAPP, enter a work center in the op./sub-op," typically occurs in the context of production planning and control when using the Computer-Aided Process Planning (CAPP) functionality. This error indicates that the system requires a work center to be specified for the operation or sub-operation in order to calculate standard values.
Cause:
- Missing Work Center: The most common cause of this error is that the operation or sub-operation in the routing does not have a work center assigned to it.
- Incorrect Configuration: The configuration of the routing or the work center may not be set up correctly, leading to the inability to calculate standard values.
- CAPP Settings: The CAPP settings may not be properly configured to allow for the calculation of standard values.
Solution:
Assign a Work Center:
- Go to the routing transaction (e.g., CA01 for creating a routing or CA02 for changing a routing).
- Locate the operation or sub-operation that is causing the error.
- Ensure that a valid work center is assigned to that operation or sub-operation.
Check Work Center Configuration:
- Navigate to the work center transaction (e.g., CR01 for creating a work center or CR02 for changing a work center).
- Verify that the work center is correctly configured and that it is active.
Review CAPP Settings:
- Check the CAPP settings in the system to ensure that they are correctly configured to allow for standard value calculations.
- Consult with your SAP Basis or technical team if necessary to ensure that the CAPP functionality is properly set up.
Test the Changes:
- After making the necessary changes, try to re-run the process that triggered the error to see if it has been resolved.
Related Information:
If the issue persists after following these steps, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in production planning and control.
Get instant SAP help. Start your 7-day free trial now.
CE336
You have reached the last selected characteristic
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CE335
You have reached the first selected characteristic
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CE338
The aut. calculation of std. values for this operation has been cancelled
What causes this issue? You started the calculation of standard values using the automatic selection function. Before all calculations were carried ...
CE339
CAPP data already exists for this operation
What causes this issue? You want to calculate standard values for this operation using the function for the automatic selection of CAPP elements. Ho...
Click on this link to search all SAP messages.