Do you have any question about this error?
Message type: E = Error
Message class: C7 - Scheduling
Message number: 005
Message text: All standard values not maintained in the operation
You have not maintained all of the standard values in the operation
that, according to the settings, should or have to be maintained in the
work center.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Maintain the standard values in the operation.
Error message extract from SAP system. Copyright SAP SE.
C7005
- All standard values not maintained in the operation ?The SAP error message C7005, which states "All standard values not maintained in the operation," typically occurs in the context of production planning or routing in SAP. This error indicates that the system expects standard values (like time, quantities, or costs) to be defined for a specific operation in a routing, but they are missing.
Cause:
- Missing Standard Values: The most common cause is that the standard values for the operation in the routing are not maintained. This could include missing values for setup time, processing time, or teardown time.
- Incorrect Routing: The routing being used may not be correctly set up or may not correspond to the material being produced.
- Configuration Issues: There may be issues with the configuration of the production environment or the specific operation being executed.
Solution:
Maintain Standard Values:
- Go to the routing transaction (e.g., CA01 for creating or CA02 for changing).
- Locate the specific operation that is causing the error.
- Ensure that all required standard values (like setup time, processing time, and teardown time) are filled in.
- Save the changes.
Check Routing Assignment:
- Verify that the correct routing is assigned to the material in question.
- Ensure that the routing is active and valid for the production version being used.
Review Configuration:
- If the issue persists, review the configuration settings related to production planning and routing in your SAP system.
- Consult with your SAP configuration team to ensure that all necessary settings are correctly defined.
Testing:
- After making the necessary changes, test the operation again to ensure that the error no longer occurs.
Related Information:
If the problem continues after following these steps, it may be beneficial to consult with your SAP support team or refer to SAP Notes for any known issues related to this error message.
Get instant SAP help. Start your 7-day free trial now.
C7004
No work center in the op./act. (working/operat.time via cal.in op./act.)
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
C7003
Scheduling terminated: Check lot size unit of measure
What causes this issue? The lot size cannot be converted into the quantity unit of the library network.System Response INCLUDE 'NA_ALLG_NOVERAR...
C7006
No dates found for restrictions
What causes this issue? You have maintained keys for constraints, but you have not maintained any corresponding dates. Scheduling is carried out wit...
C7007
Date for restriction could not be converted
What causes this issue? An internal error occurred when converting the dates for the constraint.System Response Scheduling is carried out without th...