Do you have any question about this error?
Message type: E = Error
Message class: APO_BAPI - Message Class for APO BAPIs
Message number: 094
Message text: A different planning version is being used
You have tried to call up data in the planning version. This was not
possible, however, as a different planning version has been used in the
same call.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
If you make more than one call, check if a planning version was set or
used in the previous calls, that differs from the currently transferred
planning version.
Error message extract from SAP system. Copyright SAP SE.
APO_BAPI094
- A different planning version is being used ?The SAP error message APO_BAPI094 indicates that a different planning version is being used in the context of Advanced Planning and Optimization (APO). This error typically arises when there is a mismatch between the planning version specified in the BAPI call and the version that is currently active or being used in the system.
Cause:
- Version Mismatch: The planning version specified in the BAPI call does not match the version that is currently set in the system for the relevant planning area.
- Incorrect Configuration: The planning version may not be correctly configured or may not exist in the system.
- User Authorization: The user may not have the necessary authorizations to access the specified planning version.
- Data Locking: There may be data locks or other processes that are preventing the use of the specified planning version.
Solution:
- Check Planning Version: Verify that the planning version you are trying to use in your BAPI call is correct and exists in the system. You can do this by navigating to the relevant planning area in the SAP APO system.
- Update BAPI Call: If the planning version is incorrect, update your BAPI call to use the correct version that matches the active version in the system.
- Authorization Check: Ensure that the user executing the BAPI has the necessary authorizations to access the specified planning version.
- Review Configuration: Check the configuration settings for the planning version in the APO system to ensure it is set up correctly.
- Data Locking: Investigate if there are any locks on the data that might be causing the issue. You can use transaction codes like SM12 to check for locks.
- Consult Documentation: Refer to SAP documentation or notes related to the specific BAPI you are using for any additional context or troubleshooting steps.
Related Information:
/SAPAPO/SDP94
(for planning version management) and /SAPAPO/MC90
(for planning area settings) to help diagnose the issue.By following these steps, you should be able to identify the cause of the error and implement a solution to resolve it.
Get instant SAP help. Start your 7-day free trial now.
APO_BAPI093
Error when creating/changing blocks
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
APO_BAPI092
Only demand priorities 1, 5 and 6 are supported
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
APO_BAPI095
Another transactional simulation is currently being used
What causes this issue? The system attempted to access data in a transactional simulation, or to open a new transactional simulation. However, this w...
APO_BAPI096
Data has not been entered in all required fields for the key assignment
What causes this issue? It was not possible to assign an external key to internal keys. This may have the following causes: An external order number ...
Click on this link to search all SAP messages.