Message text: WBS element &1 is not part of project &2
You have specified project &V2& and initial WBS element &V1&. The
system thus tries to select all WBS elements
which belong to project &V2&, and
are on the same hierarchy level as WBS element or are subordinate to it
WBS element &V1& must also be part of project &V2&. It does not.
Correct your input.
Error message extract from SAP system. Copyright SAP SE.
AP080
- WBS element &1 is not part of project &2 ?The SAP error message AP080 indicates that a Work Breakdown Structure (WBS) element is not part of the specified project. This error typically occurs when you are trying to perform an operation (such as posting costs, creating a transaction, or assigning resources) on a WBS element that is not correctly linked to the project in the system.
Cause:
- Incorrect WBS Element: The WBS element you are trying to use may not be correctly assigned to the project.
- Project Structure: The project structure may have changed, and the WBS element may have been deleted or is no longer valid.
- Authorization Issues: You may not have the necessary authorizations to access the WBS element or project.
- Data Entry Errors: There may be a typographical error in the WBS element or project number being used.
Solution:
- Verify WBS Element: Check if the WBS element exists and is correctly assigned to the project. You can do this by navigating to the project structure in SAP (using transaction codes like CJ20N or CJ03).
- Check Project Assignment: Ensure that the WBS element is part of the project by reviewing the project hierarchy. If it is not, you may need to create a new WBS element or reassign the existing one.
- Review Authorizations: Ensure that you have the necessary permissions to access the project and WBS element. If not, contact your SAP security administrator.
- Correct Data Entry: Double-check the WBS element and project numbers for any typographical errors. Ensure that you are using the correct identifiers.
- Consult Documentation: If the issue persists, refer to SAP documentation or consult with your SAP support team for further assistance.
Related Information:
By following these steps, you should be able to resolve the AP080 error and ensure that your WBS elements are correctly linked to their respective projects.
Get instant SAP help. Start your 7-day free trial now.
AP079
WBS element &1 does not exist
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
AP078
Entering a WBS element does not make sense for several projects
What causes this issue? You have selected several projects and also entered a WBS element in the initial screen. It only makes sense to enter a WBS ...
AP081
Select valid field
What causes this issue? You tried to use the function <PF>Detail</> to branch to a detail display. However, there is no meaningful detail...
AP082
Reassigning again is not possible - save first
What causes this issue? You have already reassigned one sub-tree of the investment program. Therefore, it is only possible to reassign another sub-tr...
Click on this link to search all SAP messages.