Message number: 590
Message text: Latest start date and start date are more than 1 year apart
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Latest start time of background processing
Error message extract from SAP system. Copyright SAP SE.
00590
- Latest start date and start date are more than 1 year apart ?The SAP error message "00590 Latest start date and start date are more than 1 year apart" typically occurs in the context of project management or scheduling within SAP, particularly when dealing with project definitions, network activities, or task scheduling. This error indicates that the latest start date (the latest date by which a task can start without delaying the project) and the start date (the planned start date of the task) are more than one year apart, which is not allowed by the system's configuration.
Cause:
- Date Configuration: The dates entered for the task or project may have been set incorrectly, leading to a discrepancy of more than one year between the latest start date and the planned start date.
- Project Planning Errors: During project planning, if the dates are not aligned properly, it can lead to this error.
- System Settings: The system may have specific settings or constraints that limit the allowable range between the latest start date and the planned start date.
Solution:
- Check Dates: Review the latest start date and the planned start date for the task or project. Ensure that they are within one year of each other.
- Adjust Dates: If the dates are indeed more than one year apart, adjust either the latest start date or the planned start date to bring them within the acceptable range.
- Review Project Structure: If the error persists, review the overall project structure and dependencies to ensure that all related tasks and milestones are correctly aligned.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidelines on date settings and project planning.
- System Configuration: If necessary, consult with your SAP administrator or technical team to check if there are any system settings that need to be adjusted.
Related Information:
CJ20N
(Project Builder) or CN21
(Create Work Breakdown Structure) to access and modify project details.By following these steps, you should be able to resolve the error and ensure that your project scheduling aligns with SAP's requirements.
Get instant SAP help. Start your 7-day free trial now.
00589
Latest start date is before the start date
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
00588
Deatils about latest start date are not complete
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
00591
Invalid variant &
What causes this issue? Message 590 for the background processing: Latest start time is createdSystem Response The system issues an error message an...
00592
No authorization for displaying authorizations of user &
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.