Do you have any question about this error?
Message type: E = Error
Message class: MPE_INSTALLATION_MSG -
Message number: 035
Message text: Komponente ist dem Vorgang mit falschem Bezugsort zugeordnet
One of the following applies:
The production engineer manually assigned the component to an
individually selected network activity in the BOM transfer (transaction
CN33_N).
The reference point in the network activity was changed after the BOM
transfer.
The reference point in the BOM item was changed after the BOM transfer.
Reference points are used to assign BOM items to network activities. The
component demand (reservation) is assigned to a different network
activity than defined by the reference points.
You have the following options:
Accept the warning.
Change the reference point either in the BOM item or network activity
(using the <LS>Maintain Bill of Material</> app with the item selected
or transaction <AB>CJ20N</> with the network activity selected).
Subsequently re-explode the current BOM version.
Assign the component to a different network activity by re-exploding the
current BOM version.
Das System gibt eine Fehlermeldung aus und erlaubt Ihnen nicht, mit dieser Transaktion fortzufahren, bis der Fehler behoben ist.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
MPE_INSTALLATION_MSG035
- Komponente ist dem Vorgang mit falschem Bezugsort zugeordnet ?Get instant SAP help. Start your 7-day free trial now.
MPE_INSTALLATION_MSG034
Komponente zu Vorgang ohne Bezugsort zugeordnet
Was verursacht dieses Problem? You manually assigned the BOM item to a network activity or you created the network directly from the BOM.Systemantw...
MPE_INSTALLATION_MSG033
Referenzierter Vorgang ist nicht vorhanden
Was verursacht dieses Problem? A component demand or reservation references a network activity that does not exist.Systemantwort Every demand for...
MPE_INSTALLATION_MSG036
Komponente ist dem Vorgang nicht zugeordnet
Was verursacht dieses Problem? Why is it relevant? Every demand for an installation kit should be assigned to a network activity to define the sequ...
MPE_INSTALLATION_MSG037
Referenzierter Vorgang ist nicht vorhanden
Was verursacht dieses Problem? Why is it relevant? Every demand for an installation kit should be assigned to a network activity to define the sequ...