Message type: E = Error
Message class: MD - Material Requirements Planning (MRP)
Message number: 504
Message text: &1: Vorgang auf Komponentenebene vorziehen (U1)
The rescheduling check has calculated that the receipts of the
components are not available until too late of a date. The delay time
displayed indicates the number of workdays by which the component
receipt with the greatest delay for meeting the necessary availability
date is delayed in realation to the whole BOM structure. The delay
times for individual component receipts are added by the BOM hierarchy
levels.
This exception message appears in the MRP list for a planning run in
the main memory.
Check whether you can give preference to the receipts for the
components causing the delay. You can access these receipts by choosing
the function 'Order structure' for the receipt you are viewing.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
MD504
- &1: Vorgang auf Komponentenebene vorziehen (U1) ?Get instant SAP help. Start your 7-day free trial now.
MD503
&1: Endtermin von Komponenten in Vergangenheit (T4)
Was verursacht dieses Problem? The finish date of the order proposals for the components is in the past.Systemantwort This exception message appe...
MD502
&1: Starttermin von Komponenten in Vergangenheit (T3)
Was verursacht dieses Problem? The start date of order proposals for the components is in the past.Systemantwort This exception message appears i...
MD505
&1: Vorgang auf Komponentenebene verschieben (U2)
Was verursacht dieses Problem? The rescheduling check has determined that the receipts for the components should be changed to avoid excessive ware...
MD510
Überlauf: Mehr als 9999 Positionen in BOM bei &. Stückliste rekursiv?
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.