Do you have any question about this error?
Message type: E = Error
Message class: LP - WM-PP interface
Message number: 074
Message text: Selektion der Aufträge kann Bereitstellungsdaten verfälschen
During the WM material staging process for release order parts, the
requirement quantity and the requested quantity are determined as the
open transfer requirement (TR) quantity for each material and
production storage bin. The requirement quantity is calculated based on
the reservations of the selected orders and is accumulated for each
material and storage bin. For release order parts, the system does not
update the generated transfer requirement quantities in the
reservations since this type of material staging is not order-based,
but material-based. As a result, the open transfer requirements must be
checked against the requested quantity. Since the transfer requirements
also have no reference to the order, the quantity of all open transfer
requirements will be accumulated for each material and production
storage bin and will be determined as the open TR quantity.
If the requirement quantity is determined on the basis of all
reservations, the relation between the requirement quantity and the
requested quantity as the open TR quantity is correct. However, if the
requirement quantity is determined on the basis of only part of the
reservations, the system checks this partial quantity as the
requirement quantity against the total quantity of the open transfer
requirements in order to determine the requested quantity.
The following example illustrates this problem:
For material 'XYZ' and production storage bin '100 bin-01', five
reservations (5 orders) exist:
order 4711 50 pieces
order 4712 100 pieces
order 4713 50 pieces
order 4714 50 pieces
order 4715 100 pieces
Das System gibt eine Fehlermeldung aus und erlaubt Ihnen nicht, mit dieser Transaktion fortzufahren, bis der Fehler behoben ist.
A warehouse worker requests staging for material 'XYZ' and selectsStaging release order parts by selecting different orders only makes
sense if no open transfer requirements exist at the time when the
materials are supplied. This means that you must not request a second
staging of release order parts by selecting different orders, unless
the transfer requirements have been converted into transfer orders.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
LP074
- Selektion der Aufträge kann Bereitstellungsdaten verfälschen ?Get instant SAP help. Start your 7-day free trial now.
LP073
Angeforderte Menge ist größer als Lagerbestand
Was verursacht dieses Problem? The requested quantity is greater than the quantity that will be determined on the basis of the storage type search ...
LP072
Angeforderte Menge ist größer als notwendig
Was verursacht dieses Problem? The requested quantity is greater than the quantity that is required based on the required stock minus the storage b...
LP080
*** Allgemeine Fehlermeldungen für Protokollierung
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
LP083
Dynamische Platzvergabe im Regelkreis &1 &2 &3
Was verursacht dieses Problem? The control cycle for materieal &V1&, PVB &V2& in plant &V3& has a <GL:dynamic_storage_bi...