Do you have any question about this error?
Message type: E = Error
Message class: KA - CO Overhead Costs: Overhead, Accrual Calculation
Message number: 420
Message text: Entlastungsauftrag & ist nicht planintegriert
You want to apply overhead for a plan-integrated object (order,
project, etc). This being the case, all the credit objects must also
be integrated with planning. This means that you can use cost centers
or plan-integrated orders. The credit objects are then credited in the
plan.
However, your costing sheet contains both plan-integrated and non-plan
integrated credit objects.
No overhead can be applied.
Change your costing sheet so that only plan integrated credit objects
appear in the credits.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
KA420
- Entlastungsauftrag & ist nicht planintegriert ?Get instant SAP help. Start your 7-day free trial now.
KA419
Geben Sie ein Kostenartenintervall an
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
KA418
KoArtenInterv. & und KoArtenInterv. & überlappen
Selbsterklärende Nachricht Da SAP der Meinung ist, dass diese spezielle Fehlermeldung 'selbsterklärend' ist, wurden keine weiteren Informationen geg...
KA421
Kein gültiger Stammsatz im Verarbeitungszeitraum vorhanden
Was verursacht dieses Problem? The system could not locate master records for processing, for the time frame you entered between period &V1&...
KA422
Es müssen alle Entlastungsobjekte planintegriert sein.
Was verursacht dieses Problem? You are working in a plan version, in which integrated planning for for orders with Cost Center Accounting is active...