Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 212
Message text: &1 &2: Endeinschränkung kollidiert mit ermitteltem Ende
A constraint is set for the finish of the project element. In backward
scheduling, the system calculates the finish (latest finish) of the
project element step by step:
Actual finish of the project element (you can use the BAdI to ignore
this).
If no actual finish has been set, the system determines it from the
successor relationships of the project element.
If no actual finish was found in the previous steps, the system takes
the finish of the higher-level project element.
The system then compares the determined finish (latest finish) with the
constraint for the finish. The warning appears if the finish conflicts
with the constraint for the finish.
The system sets the finish of the constraint as the calculated finish.
Check whether the constraint for the finish is realistic.
Das System gibt eine Fehlermeldung aus und erlaubt Ihnen nicht, mit dieser Transaktion fortzufahren, bis der Fehler behoben ist.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
DPR_SHARED212
- &1 &2: Endeinschränkung kollidiert mit ermitteltem Ende ?Get instant SAP help. Start your 7-day free trial now.
DPR_SHARED211
&1 &2: Starteinschränkung kollidiert mit ermitteltem Start
Was verursacht dieses Problem? A constraint is set for the start of the project element. In forward scheduling, the system calculates the start (ea...
DPR_SHARED210
Keine Berechtigung zum Terminieren von &1 '&2'
Was verursacht dieses Problem? You do not have sufficient authorization to carry out scheduling for &V1& '&V2&'.Systemant...
DPR_SHARED213
&1 &2: Starteinschränkung kollidiert mit Ende des Terminrahmens
Was verursacht dieses Problem? The system calculated a finish date using the fixed start date and the duration of the project element. This finish ...
DPR_SHARED214
&1 &2: Endeinschränkung kollidiert mit Start des Terminrahmens
Was verursacht dieses Problem? The system calculated a start date using the fixed finish date and the duration of the project element. This fixed s...