Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 721
Message text: Auftrag & Vorgang & liegt außerhalb des Vorgangspuffers
An operation is to be dispatched so that it lies outside the operation
float. However, in the strategy profile in Customizing for capacity
planning the indicator <ZH>Only consider floats</> is set. This
specifies that the planning result only counts as error-free if the
operation lies within the operation float.
If necessary reschedule the operation
reschedule another commitment so as to increase the available capacity.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
CY721
- Auftrag & Vorgang & liegt außerhalb des Vorgangspuffers ?Get instant SAP help. Start your 7-day free trial now.
CY720
Auftrag & Vorgang &: Überlappungskonflikt mit Nachfolgervorgang &
Was verursacht dieses Problem? An operation is to be dispatched in such a way that it overlaps with thefollowing one. However no overlapping has be...
CY719
Auftrag & Vorgang &: Überlappungskonflikt mit Vorgängervorgang &
Was verursacht dieses Problem? An operation is to be dispatched in such a way that it overlaps with the preceding operation. However it was not int...
CY722
Auftrag & Vorgang & außerhalb des Puffers Vorgriffszeit + Vorgangspuffer
Was verursacht dieses Problem? An operation is to be dispatched so that it lies outside the float before production and the operation float. Howeve...
CY723
Auftrag & Vorgang & liegt außerhalb des Puffers Sicherheitszeit
Was verursacht dieses Problem? An operation is to be dispatched so that it lies outside the float after production. However, in the strategy profil...