Do you have any question about this error?
Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 345
Message text: Netzplan &/&: Der Endtermin ist ungleich dem Einschränkungstermin
The start date for the operation has the constraint that it should
finish on a particular date (constraint date). However the start date
when you want to dispatch the operation leads to a finish date which
does not correspond to the constraint date. So it is not possible to
dispatch the operation.
You should change the start date on which you want to dispatch the
operation.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
CY345
- Netzplan &/&: Der Endtermin ist ungleich dem Einschränkungstermin ?Get instant SAP help. Start your 7-day free trial now.
CY344
Netzplan &/&: Der Starttermin liegt hinter dem Einschränkungstermin
Was verursacht dieses Problem? The start date for the operation has the constraint that it should not be after a particular date (constraint date)....
CY343
Netzplan &/&: Der Starttermin liegt vor dem Einschränkungstermin
Was verursacht dieses Problem? The start date for the operation has the constraint that it should not be before a particular date (constraint date)...
CY346
Netzplan &/&: Der Endtermin liegt vor dem Einschränkungstermin
Was verursacht dieses Problem? The finish date for the operation has the constraint that it should not be before a particular date (constraint date...
CY347
Netzplan &/&: Der Endtermin liegt hinter dem Einschränkungstermin
Was verursacht dieses Problem? The finish date for the operation has the constraint that it should not finish after a particular date (constraint d...