Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 747
Message text: Maximum von &1 Tagen als Dauer des Vorgangs &2 übernommen
You want to adjust the duration of a network activity to the maximum
delivery time or replenishment lead time of all allocated material
components.
The system only calculates using the allocated material components that
have the indicator <ZH>Alignment finish date</> set. The maximum
duration comes from
the planned delivery time when the material components are procured
externally
the total replenishment lead time when the material components are
produced internally or the in-house production time if the total
replenishment lead time is not maintained in the material master
Make sure that the <ZH>Alignment finish date</> indicator on the
component detail screen of the activity is set for all material
components allocated to the activity.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
CN747
- Maximum von &1 Tagen als Dauer des Vorgangs &2 übernommen ?Get instant SAP help. Start your 7-day free trial now.
CN746
Kundenauftragsposition & nicht für Einzelbestand zulässig
Was verursacht dieses Problem? You changed a material component allocation to a sales order item.Systemantwort The sales order item you entered d...
CN745
Änderung der Kundenauftragsposition kann Bedarfsplanung beeinflussen
Was verursacht dieses Problem? You changed a material component allocation to a sales order item.Systemantwort The system does not check whether ...
CN748
Keine Berechtigung zur Pflege von Planprimärbedarfen
Was verursacht dieses Problem? You want to generate planned independent requiremens but do not have the necessary authorization.Systemantwort The...
CN749
Fehler bei der Generierung eines Planprimärbedarfes
Was verursacht dieses Problem? An error occurred when planned independent requirements were being generated.Systemantwort The system does not gen...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.