How To Fix CN747 - Maximum von &1 Tagen als Dauer des Vorgangs &2 übernommen


SAP Error Message - Details

  • Message type: E = Error

  • Message class: CN - Meldungen für Netzpläne

  • Message number: 747

  • Message text: Maximum von &1 Tagen als Dauer des Vorgangs &2 übernommen

  • Show details Hide details
  • Was verursacht dieses Problem?

    You want to adjust the duration of a network activity to the maximum
    delivery time or replenishment lead time of all allocated material
    components.

    Systemantwort

    The system only calculates using the allocated material components that
    have the indicator <ZH>Alignment finish date</> set. The maximum
    duration comes from
    the planned delivery time when the material components are procured
    externally
    the total replenishment lead time when the material components are
    produced internally or the in-house production time if the total
    replenishment lead time is not maintained in the material master

    Wie behebe ich diesen Fehler?

    Make sure that the <ZH>Alignment finish date</> indicator on the
    component detail screen of the activity is set for all material
    components allocated to the activity.

    Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE


Smart SAP Assistant

  • Was ist die Ursache und Lösung für den SAP Fehler CN747 - Maximum von &1 Tagen als Dauer des Vorgangs &2 übernommen ?




    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Zugehörige SAP-Fehlermeldungen

Klicken Sie auf die Links unten, um die folgenden verwandten Nachrichten anzuzeigen:

Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker